| UNSPECIFIED | DSINSPECTION | | DEL ORO SIGN OFF | |
|
| ENV HEALTH RELEASE | ALANA KONG | PASS | | 5/6/2022 12:06:59 PM
Hold for del oro water approval on review and camp fire septic report. see notes on review below.
|
|
05/11/2022 | UNDERGROUND PLUMBING | RICHARD PRATT | FAIL | | 5/11/2022 5:29:28 AM
rpratt changed Inspection Date/Time from 05/11/2022 03:00 PM to 05/11/2022 10:30 AM
5/11/2022 11:31:25 AM
Provide a 10' head hydrostatic test for DWV.
Remove gravel for plumbing trenches and provide sand or clean fill.
Recall inspection when completed
|
|
05/16/2022 | FOUNDATION/FOOTINGS | RICHARD PRATT | PASS | Underslab plumbing | 5/16/2022 2:39:20 PM
rpratt changed Inspection Type from FOUNDATION/FOOTINGS to UNDER SLAB PLUMBING
|
|
05/11/2022 | FOUNDATION/FOOTINGS | RICHARD PRATT | PASS | Set Backs | 5/11/2022 5:29:32 AM
rpratt changed Inspection Date/Time from 05/11/2022 03:00 PM to 05/11/2022 10:30 AM
5/11/2022 11:31:29 AM
rpratt changed Inspection Type from FOUNDATION/FOOTINGS to SETBACKS
|
|
05/17/2022 | FOUNDATION/FOOTINGS | RICHARD PRATT | PASS | House Mono-Pour | 5/17/2022 11:33:02 AM
Forms footings and rebar- Approved
Pre pour slab - Approved
5/31/2022 11:04:16 AM
BUILDING PAD COMPACTION/ SOILS REPORT ATTACHED.
|
|
05/18/2022 | UFER GROUND | RICHARD PRATT | FAIL W/RE-INSP FEE | AM REQUEST | 5/18/2022 1:39:09 PM
Ufer ground was not installed at previous inspection.
Now it is buried in concrete without verification.
|
|
05/18/2022 | PRE-SLAB | RICHARD PRATT | FAIL W/RE-INSP FEE | Garage slab and footings | 5/18/2022 5:41:32 AM
rpratt changed Inspection Date/Time from 05/17/2022 12:00 PM to 05/18/2022 1:00 PM
5/18/2022 1:39:04 PM
Contractor said the garage footings and slab were not going to be poured until today, 18 May 2022.
Contractor poured footings and slab without inspection.
Obtain an Engineer letter of approval for garage footings and slab.
Submit to the Building Dept. for Approval.
|
|
06/07/2022 | SHEARWALL/B.W.P.-INT | SCOTT YOUNG | PASS | | |
|
06/07/2022 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | PASS | | 6/8/2022 6:25:41 AM
H- 1 clips not installed on south wall
A-35 clips required at gable end at back of house.
|
|
06/08/2022 | ROOF NAIL | SCOTT YOUNG | PASS | am request adam if possible | 6/8/2022 6:25:45 AM
Radiant barrier not required. Sheet S2.6. See attachments for pictures.
|
|
06/14/2022 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | FAIL | AM INSPECTION REQUESTED | 6/14/2022 1:03:35 PM
1. Provide blocking/solid support for HVAC supply registers.
2. Cover HVAC supply registers to protect from construction debris.
3. Leaking DWV tee fitting at lavatory vent -repair, replace or equal.
4. Provide approved rat proofing (mortar or grout or equal) at exterior wall/ sill plate notch for kitchen island sink vent pipe.
5. Provide nail plate at fire sprinkler riser/top plate in garage & electrical circuits (kitchen peninsula)/ top plate.
Ok to insulate. Corrections are required to remain exposed for re-inspection.
Recall inspection.
|
|
06/15/2022 | 4-WAY ROUGH FRAME | CHRISTOPHER ROBERTS | PASS | | 6/15/2022 12:47:52 PM
All prior corrections have been resolved.
OK to fully insulate.
|
|
07/15/2022 | GAS TEST | CHRISTOPHER ROBERTS | FAIL | | 7/15/2022 4:09:08 PM
Gas test - approved
** do not backfill trench until you provide a 6" bed of sand above and 6" below gas pipe! **
Call for re-inspection when complete
|
|
07/18/2022 | SHOWER PAN/TUB TEST | RANDALL SMITH | PASS | | 7/18/2022 4:58:46 PM
Passed
|
|
07/25/2022 | PGE ELECTRIC TAG | ADAM KINGSLEY | PASS | | |
|
07/27/2022 | UNDERGROUND WATER PI | RANDALL SMITH | PASS | | 7/27/2022 12:11:16 PM
Passed
7/27/2022 4:33:47 PM
Passed
|
|
10/27/2022 | CAL FIRE FINAL INSPE | CHRIS BOYD | PASS | | |
|
10/31/2022 | PW FINAL | PWROADS | PASS | | 10/31/2022 2:38:42 PM
PASSED PER R1 EMAIL DATED 10/31/2022
|
|
11/09/2022 | **PERMIT FINAL | CHRISTOPHER ROBERTS | FAIL | | 11/9/2022 6:51:34 AM
croberts changed Inspection Date/Time from 11/09/2022 08:00 AM to 11/09/2022 1:00 PM
11/9/2022 2:12:24 PM
1. Replace broken switch cover in garage.
2. Humidistat required in both bathrooms.
3. Finish closet molding in bedroom #1
4. Install shower head and handle in master bathroom.
5. Finish installing doorknob in master bath.
6. Install fan vent in master bath.
7. Provide dead front fully labeled on main service panel.
Complete work and call for re-inspection.
** okay to move in
|
|
12/08/2022 | **PERMIT FINAL | RANDALL SMITH | PASS | | 12/8/2022 9:35:09 AM
All previous corrections have been completed. Passed
12/8/2022 9:35:57 AM
All previous corrections have been completed. Passed
|
|