03/24/2022 | FOUNDATION/FOOTINGS | SCOTT YOUNG | PASS | eTRAKiT Inspection Request | 3/21/2022 7:03:44 AM
3/21/2022 7:03 AM NORTH VALLEY BUILDING SYSTEMS INC
AM / Morning inspection if possible please...Thank you!
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: BRET@NORTHVALLEYBUILDING.COM
|
|
04/05/2022 | PRE-SLAB | RANDALL SMITH | PARTIAL | 058549-01 - Scheduled by IVR. | 4/5/2022 5:02:27 PM
Partial pre slab inspection on south portion passed. Completed pier and foundation/ footing inspection on storage portion of building. Completed under slab plumbing inspection. Photos will be taken of rebar in gun vault footings. Partial until photographs submitted. Will call for inspection of other portion pre slab
4/5/2022 5:25:03 PM
Partial pre slab inspection on south portion passed. Completed pier and foundation/ footing inspection on storage portion of building. Completed under slab plumbing inspection. Photos will be taken of rebar in gun vault footings. Partial until photographs submitted. Will call for inspection of other portion pre slab
|
|
04/11/2022 | PRE-SLAB | ADAM KINGSLEY | PARTIAL | eTRAKiT Inspection Request | 4/6/2022 11:31:23 AM
4/6/2022 11:31 AM NORTH VALLEY BUILDING SYSTEMS INC
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
4/11/2022 11:45:00 AM
Remaining slab approved.
Revision or equal required for added CMU infill/footings for vault & plumbing for bathroom & mop sink
|
|
04/29/2022 | UNDERGROUND ELECTRIC | ADAM KINGSLEY | PASS | 059153-01 - Scheduled by IVR. | 4/29/2022 11:06:35 AM
akingsley changed Inspection Type from ROUGH ELECTRICAL to UNDERGROUND ELECTRIC
4/29/2022 11:14:33 AM
Electric trench to electric service/pole-approved
|
|
05/24/2022 | MASONRY GROUT | RANDALL SMITH | PASS | 059712-01 - Scheduled by IVR. | 5/24/2022 4:19:43 PM
Plans call for special inspection of gun vault. Inspected rebar and took photos of gun vault. Advised contractor to do special inspection as plans called for. Passed
|
|
06/16/2022 | ROOF PRE-INSPECTION | ADAM KINGSLEY | PASS | eTRAKiT Inspection Request | 6/14/2022 10:03:56 AM
6/14/2022 10:03 AM NORTH VALLEY BUILDING SYSTEMS INC
Inspect Top of Decking at Safe Room
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
6/16/2022 4:04:35 PM
Vault roof pan -approved
|
|
08/08/2022 | 4-WAY ROUGH FRAME | RICHARD PRATT | PASS | eTRAKiT Inspection Request | 8/3/2022 9:38:06 AM
8/3/2022 9:38 AM NORTH VALLEY BUILDING SYSTEMS INC
AM/Morning Inspection please...Thank you!
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
8/8/2022 5:16:15 AM
Rpratt changed Inspection Date/Time from 08/08/2022 08:00 AM to 08/08/2022 11:30 AM
8/8/2022 5:19:31 AM
Rpratt changed Inspection Date/Time from 08/08/2022 08:00 AM to 08/08/2022 11:30 AM
8/8/2022 12:36:59 PM
4 way frame and trades - Approved
|
|
08/15/2022 | SHEARWALL/B.W.P.-INT | RANDALL SMITH | PASS | eTRAKiT Inspection Request | 8/12/2022 11:30:21 AM
8/12/2022 11:30 AM NORTH VALLEY BUILDING SYSTEMS INC
PM / Afternoon Inspection Please...Thank you!
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
8/15/2022 3:54:50 PM
Passed
|
|
09/28/2022 | **PERMIT FINAL | RANDALL SMITH | FAIL | eTRAKiT Inspection Request | 9/26/2022 1:33:56 PM
9/26/2022 1:33 PM NORTH VALLEY BUILDING SYSTEMS INC
Morning / AM inspection please...Thank you!
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
9/28/2022 1:02:38 PM
1. Provide final approval from Cal Fire.
2. Provide final approval from Butte County Public Works.
4. Provide a post elevation certificate to the permit center.
5. Provide a special inspection report for the high strength bolting to the permit center
7. Insulate the water main.
8. Provide vacuum breakers on the hose bibs.
9.Secure air compressor to the concrete pad.
10. Complete installation of bathroom light or cover open conductors.
11. Install humidistat in bathroom for exhaust fan.
12. Seal penetration in sw wall (copper piping.)
13. Install a 90 degree elbow pointing dow on water heater PTR a valve. Paint cover or equal pvc piping and seal penetration exiting the exterior siding.
14. Call for reinspection when corrections are completed.
|
|
09/30/2022 | UNDER CONST CERT | PHILO HUNT | PASS | | |
|
09/30/2022 | POST ELEVATION CERT | PHILO HUNT | PASS | | |
|
10/05/2022 | CAL FIRE FINAL INSPE | TROY HAND | PASS | | 10/5/2022 3:23:18 PM
Met all fire criteria
|
|
10/06/2022 | **PERMIT FINAL | CHRISTOPHER ROBERTS | PASS | eTRAKiT Inspection Request | 10/5/2022 9:00:36 AM
10/5/2022 9:00 AM NORTH VALLEY BUILDING SYSTEMS INC
AM/Morning Inspection please....Thank you!
Contact Name: NORTH VALLEY BUILDING SYSTEMS INC
Site Address: 9207 STANFORD LN
Phone: 5303457296
e-Mail: TROY@NORTHVALLEYBUILDING.COM
10/6/2022 6:37:16 AM
croberts changed Inspection Date/Time from 10/06/2022 08:00 AM to 10/06/2022 12:00 PM
10/6/2022 12:43:18 PM
All prior corrections have been resolved.
Permit final - Approved
|
|
03/24/2023 | ENV HEALTH RELEASE | BISMA KHAN | NOT REQUIRED | | |
|