| NPDES | PWLANDDEV | NOT REQUIRED | | |
|
11/05/2021 | UNDER SLAB PLUMBING | ADAM KINGSLEY | PASS | | 11/5/2021 5:05:18 PM
Setbacks also included
|
|
11/05/2021 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PASS | | 11/5/2021 5:22:21 PM
Eufer ground also included
|
|
11/17/2021 | PRE-SLAB | ADAM KINGSLEY | PASS | 055817-02 - Scheduled by IVR. | 11/17/2021 2:59:59 PM
Dwelling & garage
|
|
02/03/2022 | TAG ELECTRIC | ADAM KINGSLEY | PASS | | 2/3/2022 3:37:05 PM
Construction power approved. 200A -SFD
|
|
03/22/2022 | TRUSS ROOF | RANDALL SMITH | PASS | | |
|
03/22/2022 | SHEARWALL/B.W.P.-INT | RANDALL SMITH | PASS | | |
|
03/22/2022 | SHEARWALL/B.W.P.-EXT | RANDALL SMITH | FAIL | | 3/22/2022 1:17:12 PM
Detail 1/ S6-1 missing A35 clips at top and bottom of window header and sill. Install per plans or equal. Ok to proceed.
|
|
03/22/2022 | ROOF NAIL | RANDALL SMITH | PASS | | 3/22/2022 1:17:17 PM
1. Remove shiners in roof sheathing. Ok to proceed. Shiner removal to be checked at 4 way inspection
|
|
05/12/2022 | 4-WAY ROUGH FRAME | SCOTT YOUNG | FAIL | 059349-01 - Scheduled by IVR. | 5/13/2022 6:10:35 AM
Romex running through truss webs laying on or right up against gang nails. Separate and secure.
If using staples make sure lay romex flat,not on its side.
Came back 1 1/2 hours later to check as asked by contractor, still missed a lot .
Complete and call back for reinspection.
|
|
05/18/2022 | 4-WAY ROUGH FRAME | RANDALL SMITH | PASS | 059520-01 - Scheduled by IVR. | 5/18/2022 4:54:03 PM
Verified corrections from previous 4 way inspection.
|
|
08/24/2022 | GAS TEST | CHRISTOPHER ROBERTS | PASS | 061707-02 - Scheduled by IVR. | 8/24/2022 6:48:15 AM
croberts changed Inspection Date/Time from 08/24/2022 08:00 AM to 08/24/2022 11:30 AM
8/24/2022 11:38:30 AM
Gas test - approved
|
|
09/15/2022 | PGE GAS TAG | RICHARD PRATT | PASS | NEEDS TAG | 9/15/2022 5:06:13 AM
rpratt changed Inspection Date/Time from 09/15/2022 08:00 AM to 09/15/2022 08:30 AM
9/15/2022 6:03:11 AM
rpratt changed Inspection Date/Time from 09/15/2022 08:30 AM to 09/15/2022 09:30 AM
9/15/2022 9:44:51 AM
PG&E Gas Meter Release - Approved
|
|
11/02/2022 | **PERMIT FINAL | RICHARD PRATT | FAIL | 063173-01 - Scheduled by IVR. | 11/2/2022 1:46:53 PM
1. Complete HERS Documentation with Cheers or CalCerts.
2. Obtain Cal Fire Final Approval.
3. Obtain City of Biggs Final Approval.
4. Complete Solar installation and Final.
5. Extend clean out to be flush with finish surface and seal to prevent insect and rodent intrusion. Garage and Kitchen sink
6. Remove insulation from the FAU pan in the attic.
7. Provide GFCI Protection for the kitchen receptacles- check all
8. Wrap all exterior water piping to protect from freezing.
9. Repair wiring to the Fire Sprinkler bell, did not ring after a minute.
10. Install missing Drier Breaker or a cover in the MSP.
11. Recall inspection when completed.
|
|
11/10/2022 | CAL FIRE FINAL INSPE | TROY HAND | PASS | | 11/10/2022 3:45:01 PM
Needs to cover opening or install circuit breaker in dryer slot. all other fire criteria met
11/16/2022 2:12:18 PM
Applicant has placed a circuit breaker in the opening.
|
|
11/30/2022 | **PERMIT FINAL | CHRISTOPHER ROBERTS | PARTIAL | | 11/30/2022 6:31:08 AM
croberts changed Inspection Date/Time from 11/30/2022 08:00 AM to 11/30/2022 1:30 PM
11/30/2022 3:23:11 PM
Most of corrections have been completed.
* waiting for solar final
* City of Biggs will sign off on final when solar is finaled.
|
|
| CITY OF BIGGS FINAL | CITY OF BIGGS | PASS | | |
|