| NPDES | PWLANDDEV | | | |
|
04/11/2022 | ROUGH FRAME | SCOTT YOUNG | FAIL | 058709-01 - Scheduled by IVR. | 4/12/2022 6:02:31 AM
1. Missing anchor bolts through out garage , required within 12 " of any sole plate break.
2. They have used some 1/2" redheads , pull test from third party required.
3. Garage door and man door headers not nailed through king studs. Min. Of 6 , 16 penny stitched .
4. They have added on to the existing front porch balcony, this was not included in the plans submitted.
5. New main panel has been added on to house without permits and is not tagged. Contractor says a lot of switches and receptacles are not working since they changed out main panel.
6. Garage roof plans show 1/4" fall per foot. The roof has been built and has no fall, actually has small slope back towards house.
7. Letter from engineer required for pull test on all anchors in the garage.and column footings for balcony.
8. Either build to match approved plans or resubmit with changes.
|
|
05/17/2022 | ROUGH FRAME | ADAM KINGSLEY | CANCELLED | Cancelled on 5/17/2022 at 9:34 AM | |
|
06/29/2022 | ROUGH FRAME | ADAM KINGSLEY | CANCELLED | Cancelled on 6/29/2022 at 1:15 PM | |
|
07/01/2022 | ROUGH FRAME | RANDALL SMITH | FAIL | REQ PM | 7/1/2022 4:09:52 PM
1. Provide double 2x6 joist at edge with Simpson HUS 26-2 hangar on balcony as per plan.
2. Finish installing Simpson DTT 1 z tension tie at joist blocking to balcony joist as per plan.
3. Provide 3 by 3 inch steel washers on new anchor bolts.
4. Provide pull test for epoxied anchor bolts.
5. Provide engineer approval for change in redwood deck material to osb panels with weather proof covering.
6. Obtain a permit for damage to back of house.
7. Remove trim to show 6 inch edge nailing of exterior siding
8. Call for reinspection when corrections are completed.
Items not addressed from previous 4 way inspection.
2. They have used some 1/2%34 redheads , pull test from third party required.
5. New main panel has been added on to house without permits and is not tagged. Contractor says a lot of switches and receptacles are not working since they changed out main panel.
|
|
07/15/2022 | 4-WAY ROUGH FRAME | RICHARD PRATT | PASS | 060943-01 - Scheduled by IVR. | 7/15/2022 12:37:42 PM
All previous correction items completed
4 way frame and trades - Approved
No pull test required on Titens
|
|
06/27/2023 | PIER/COLUMN FOOTINGS | CHRISTOPHER ROBERTS | PASS | 067426-01 - Scheduled by IVR. | 6/28/2023 2:56:11 PM
footings/slab - APPROVED
|
|
07/05/2023 | ROUGH MECHANICAL | RICHARD PRATT | PASS | 067556-02 - Scheduled by IVR. | 7/5/2023 3:47:43 PM
Rough mechanical- mechanical
7/5/2023 3:50:47 PM
Rough mechanical- mechanical
|
|
07/05/2023 | ROUGH FRAME | RICHARD PRATT | PASS | 067556-01 - Scheduled by IVR. | 7/5/2023 3:47:48 PM
Rough framing - Approved
7/5/2023 3:50:50 PM
Rough framing - Approved
|
|