Permit No. B20-1843 Permit Type   NRES NON RESIDENTIAL Site Address   1 GILLICK WAY
OROVILLE, CA 95965
Applied   07/01/2020 Applicant   BARBARA NORMAN
Approved   11/04/2020 Owner   COUNTY OF BUTTE
Issued   11/04/2020 Contractor   D H SLATER & SON INC
Parent Permit No.   Description   STORAGE AND MORGUE B (6432) S1 (4558) COV (331)
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 02/28/1850ENV HEALTH RELEASEYVETTE CASTANONVOIDED (DAH 7/14/2020)7/14/2020 11:38:06 AM Inspection voided by DAH.

 12/15/2020FOUNDATION/FOOTINGSADAM KINGSLEYPASS12/15/2020 10:20:49 AM Setbacks & pier footings also included. Ok for concrete placement. Special inspection report for EOR structural observation & concrete compressive strength required. 2/17/2021 12:10:06 PM SPECIAL INSPECTION RESULTS FOR REINFORCEMENT AND CONCRETE COMPRESSIVE STRENGTH ATTACHED. ENGINEER OF RECORD OBSERVATION REPORT ATTACHED.

 01/14/2021UNDER SLAB PLUMBINGADAM KINGSLEYPARTIALpm request1/14/2021 3:25:16 PM Underslab cast DWV approved, ok to backfill. Underslab trap primers to be inspected at pre-slab.

 02/12/2021UNDER SLAB PLUMBINGADAM KINGSLEYPASS2/12/2021 9:03:45 AM Trap primer piping verified. 2/17/2021 12:08:43 PM UNDER SLAB DRAIN/WASTE PLAN REVISION ATTACHED. FIELD APPROVED.

 02/16/2021PRE-SLABADAM KINGSLEYPARTIAL2/12/2021 9:03:55 AM akingsley changed Inspection Date/Time from 02/12/2021 08:30 AM to 02/16/2021 08:30 AM 2/16/2021 10:24:30 AM akingsley changed Inspection Date/Time from 02/16/2021 10:00 AM to 02/16/2021 2:15 PM 2/16/2021 4:42:57 PM Vehicle bays (construction pour #2 as noted on control joint plan) excluded, not ready. Remaining building interior approved for concrete placement. 2/17/2021 12:12:38 PM BODY SCALE REINFORCEMENT ENGINEER REVISION ATTACHED

 03/22/2021PRE-SLABADAM KINGSLEYPASS

 03/22/2021CMU 1ST POURADAM KINGSLEYFAIL3/22/2021 5:30:22 PM East and North elevation exterior walls not completed. Remaining exterior and interior walls inspected. 1. Type 2 walls horizontal reinforcement installed 16"oc. RFI from EOR missing stamp/signature. Provide written approval (sealed by EOR) or equal.

 03/24/2021CMU 1ST POURADAM KINGSLEYFAIL3/23/2021 4:24:19 PM North elevation not completed at present. Inspected East elevation wall, pending the following 1. Type 2 walls horizontal reinforcement installed 16%34oc. RFI from EOR missing stamp/signature. Provide written approval (sealed by EOR) or equal Reschedule next day. 3/23/2021 4:25:58 PM akingsley changed Inspection Date/Time from 03/23/2021 to 03/24/2021 3/24/2021 4:43:24 PM 1. Extend reinforcement above lift to provide minimum required lap splice at the following locations: -Vertical #5 and additional #5 jamb reinforcement at openings per detail 1/S1.3 located at staff corridor side door, all openings at north wall between autopsy and NW corner and several locations on interior walls. -NW corner doubled vertical #5 per detail 2/S1.3 -single vertical #5 at opposing ends of control joints at several locations throughout. Received engineer letter for change to type 2 wall, attached.

 03/25/2021CMU 1ST POURADAM KINGSLEYPASS3/25/2021 8:46:40 AM Previous corrections are completed. Type 2 walls installed with horizontal #5 at 16" oc per engineer revision. 4/28/2021 12:23:07 PM SPECIAL INSPECTION REPORTS ATTACHED (2) TWO FILES

 04/14/2021MASONRY LIFTSADAM KINGSLEYPARTIAL2nd of 4 lifts4/13/2021 3:31:55 PM akingsley changed Inspection Date/Time from 04/13/2021 03:30 PM to 04/14/2021 1:00 PM 4/14/2021 3:05:28 PM 2nd lift of 4 -approved. 4/28/2021 12:09:59 PM SPECIAL INSPECTION REPORT ATTACHED.

 05/19/2021MASONRY LIFTSADAM KINGSLEYPASS3rd of 4 lifts5/19/2021 8:21:06 PM 3rd of 4 lifts -approved.

 05/26/2021MASONRY LIFTSADAM KINGSLEYPASSLast CMU Lift -PM Request5/26/2021 4:11:41 PM 4th/final lift for building -approved

 07/19/2021ROUGH MECHANICALADAM KINGSLEYPARTIALDuctwork to be concealed7/19/2021 3:55:13 PM Under roof ducts only -ok to insulate.

 07/26/2021ROOF FRAME/SHEATHINGADAM KINGSLEYFAIL7/27/2021 6:16:07 AM Morgue roof frame 1. Provide written approval from engineer of record for a) metal roof deck /ledger connection fix for parallel condition -welded steel tube filler; b) incorrect beam length with welded shear tabs at entry staff corridor. 2. Roof deck puddle welds appear to have burnt through decking at several locations. Provide written approval from engineer of record or acceptance from special inspection. Note: Partial inspection, structural framework only, roof nailing & mechanical curb/penetrations not complete at present. Attached: engineer fix for retrofit beam embed & revision to mechanical curb/roof penetration 8/2/2021 6:12:55 AM ITEM 1-a & 1-b CORRECTED. EOR LETTERS ATTACHED.

 08/18/2021ROUGH PLUMBINGWOODY TOWNSENDPARTIALPM REQUEST8/16/2021 4:24:22 AM BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES) 8/19/2021 7:29:54 AM All rough DWV top out test approved.

 08/18/2021ROUGH FRAMEWOODY TOWNSENDCANCELLEDPM REQUEST8/16/2021 4:24:06 AM BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES)

 08/19/2021PGE ELECTRIC TAGWOODY TOWNSENDPASSPM REQUEST8/16/2021 4:23:50 AM BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES) 8/19/2021 7:30:09 AM wtownsend changed Inspection Type from ROUGH ELECTRICAL to PGE ELECTRIC TAG

 08/23/2021PGE ELECTRIC TAGADAM KINGSLEYPASS8/22/2021 9:39:58 PM Contact Travis in am. 8/23/2021 4:00:24 PM Retag 600A electric service, new address.

 08/23/2021FOUNDATION/FOOTINGSADAM KINGSLEYPARTIAL8/23/2021 4:00:31 PM Trash enclosure footings

 08/25/2021ROUGH PLUMBINGADAM KINGSLEYPARTIAL8/25/2021 2:40:33 PM 1. Hydronic HVAC piping not completed at present. Complete installation and test. 2. Provide separation of dissimilar materials at copper condensate drain pipes & steel supports. Water supply (hot & cold cu) & cast iron DWV test & installation-approved. Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection. 8/25/2021 2:42:12 PM 1. Hydronic HVAC piping not completed at present. Complete installation and test. 2. Provide separation of dissimilar materials at copper condensate drain pipes & steel supports. Water supply (hot & cold cu) & cast iron DWV test & installation-approved. Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection.

 08/25/2021ROUGH MECHANICALADAM KINGSLEYPARTIAL8/25/2021 2:42:20 PM Concealed mechanical equipment/ductwork in wall cavities only -approved. Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection 1. Rooftop & ceiling space mechanical rough in not complete at present.

 08/25/2021ROUGH FRAMEADAM KINGSLEYPARTIAL8/25/2021 2:42:28 PM Pending special inspection reports from roof frame inspection.

 08/25/2021ROUGH ELECTRICALADAM KINGSLEYPARTIAL8/25/2021 2:42:36 PM Electrical components (raceways, device boxes, including fire alarm system) within concealed wall cavities only- approved. Ok to cover walls only. All Circuit conductors & electric sub panel rough in not completed at present.

 08/25/2021UNDERGROUND PLUMBINGADAM KINGSLEYPASS8/25/2021 2:42:44 PM Sand/oil separator & exterior drain pipe.

 09/02/2021GAS PIPINGADAM KINGSLEYPARTIAL9/2/2021 12:42:30 PM Concealed piping & test -approved, ok to cover. Remaining piping branches to boilers & water heaters not installed at present.

 09/02/2021FOUNDATION/FOOTINGSADAM KINGSLEYPARTIAL9/2/2021 3:06:42 PM GENERATOR PAD. CAST WITHOUT INSPECTION. VERIFIED VIA PHOTOGRAPHIC EVIDENCE. PENDING SPECIAL INSPECTION REPORT 1/10/2022 2:48:08 PM SPECIAL INSPECTION REPORTS ATTACHED. CONCRETE FC & REINFORCMENT

 09/15/2021LIGHT STANDARD FTGADAM KINGSLEYPARTIAL9/15/2021 6:45:34 PM Parking lot light standards, except two at front of building

 09/20/2021TAG NATURAL GASADAM KINGSLEYPASS9/20/2021 12:21:39 PM Commercial - CNG.

 10/26/2021ROOF FRAME/SHEATHINGADAM KINGSLEYPASS10/26/2021 3:09:04 PM PREVIOUS ROOF FRAME CORRECTIONS COMPLETED. ATTACHED SPECIAL INSPECTION FIELD WELDING & DECK PINNING REPORT.

 11/04/2021T-BAR CEILINGADAM KINGSLEYPARTIAL11/4/2021 6:10:14 PM T-Bar inspection: 1. Missing seismic restraints throughout. Install per notes 5 & 6/A6.2 2. Locker room area not complete. 3. Missing light fixtures in Decomp room.

 11/04/2021ROUGH FRAMEADAM KINGSLEYPASSAM REQUEST11/4/2021 10:30:54 AM akingsley changed Inspection Date/Time from 11/04/2021 09:00 AM to 11/04/2021 4:30 PM 11/4/2021 6:09:58 PM akingsley changed Inspection Type from 4-WAY ROUGH FRAME to ROUGH FRAME 1/10/2022 2:51:02 PM SPECIAL INSPECTION REPORT ATTACHED. GLASS MASONRY WINDOWS, POST INSTALLED ANCHORS AT STAIRS & GENERATOR

 11/04/2021ROUGH MECHANICALADAM KINGSLEYPARTIAL11/4/2021 6:18:51 PM Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed. Plumbing- Boilers and equipment room not completed. Framing-pass Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry. Note: Need special inspection reports for generator foundation pad concrete compressive strength

 11/04/2021ROUGH PLUMBINGADAM KINGSLEYPARTIAL11/4/2021 6:18:59 PM Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed. Plumbing- Boilers and equipment room not completed. Framing-pass Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry. Note: Need special inspection reports for generator foundation pad concrete compressive strength

 11/04/2021ROUGH ELECTRICALADAM KINGSLEYPARTIAL11/4/2021 6:19:07 PM Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed. Plumbing- Boilers and equipment room not completed. Framing-pass Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry. Note: Need special inspection reports for generator foundation pad concrete compressive strength

 11/10/2021SHOWER PAN/TUB TESTADAM KINGSLEYPASSPM REQUEST11/10/2021 1:42:43 PM Two (2) accessible shower pans

 11/10/2021T-BAR CEILINGADAM KINGSLEYPASS11/10/2021 1:43:02 PM Previous T-bar ceiling corrections completed.

 01/03/2022ROUGH PLUMBINGADAM KINGSLEYPASS1/3/2022 1:20:45 PM Previous items addressed/completed.

 01/03/2022ROUGH MECHANICALADAM KINGSLEYPASS1/3/2022 1:20:53 PM Previous items addressed/completed.

 01/03/2022ROUGH ELECTRICALADAM KINGSLEYPASS1/3/2022 1:21:01 PM Previous items addressed/completed. 1/10/2022 2:49:17 PM SPECIAL INSPECTION REPORT ATTACHED FOR GENERATOR POST INSTALLED ANCHORS.

 11/04/2021LIGHT STANDARD FTGADAM KINGSLEYPASS11/4/2021 6:10:06 PM Remaining parking lot light standards -approved 1/10/2022 2:47:16 PM SPECIAL INSPECTION REPORT -REINFORCEMENT. ATTACHED

 02/28/1850NPDESPWROADSVOIDED (CJ 1/26/2022)1/26/2022 11:46:17 AM Inspection voided by CJ.

 02/28/1850LAND DEV FINALPWLANDDEVVOIDED (CJ 1/26/2022)1/26/2022 11:47:49 AM Inspection voided by CJ.

 01/27/2022**PERMIT FINALADAM KINGSLEYFAIL1/27/2022 6:53:05 PM 1. Provide knee protection for sink drain pipes at the following sinks: Evidence processing, Login processing (morgue), break room, grossing lab and forensic lab. 2. Provide GFCI protection for receptacles within 6' of sink at Decomp workbench (two receptacles nearest sink). 3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear. 4. Provide Fire Marshal Final clearance and final permit B20-2402 (fire alarm system). 5. Provide energy compliance documents for required acceptance tests: NRCA-ENV-02-F NRCA-LTI-02 & 04-A NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A Exterior disabled access compliance, parking & egress elements not included and will need to be inspected prior to TCO consideration. Items 1-4 require correction prior to TCO consideration.

 01/31/2022**PERMIT FINALADAM KINGSLEYFAIL1/31/2022 4:29:38 PM Previous corrections are completed except: ALK 1/27/2022 6:53:05 PM 1. Provide knee protection for sink drain pipes at the following sinks: Evidence processing, Login processing (morgue), break room, grossing lab and forensic lab. 2. COMPLETED 3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear. 4. Provide Fire Marshal Final clearance. REINSPECTION: FM provided partial clearance. 5. Provide energy compliance documents for required acceptance tests: NRCA-ENV-02-F NRCA-LTI-02 & 04-A NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A EXTERIOR REINSPECTION (no access to interior) 6. Provide posted address number(s) on the building. 7. Mini split disconnect fuses missing at West elevation ground level unit. 8. Exposed conductors at building SW corner. Terminate conductors in a listed box, conduit, device or equal. 9. Install Generator fuel tank hazardous material signage, see Fire Marshal corrections. 10. Provide Fire Department access key for FD lock box. 11. Remove construction debris from public areas or job site or equal. Note: Security fencing & gates not installed at present.

 02/02/2022**PERMIT FINALADAM KINGSLEYFAIL2/2/2022 6:11:55 PM Previous corrections are completed except: 1. COMPLETED 2. COMPLETED 3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear. 4. Provide Fire Marshal Final clearance. REINSPECTION: FM provided partial clearance. 5. Provide energy compliance documents for required acceptance tests: NRCA-ENV-02-F NRCA-LTI-02 & 04-A NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A 6. COMPLETED 7. N/A COMPLETED 8. Exposed conductors at building SW corner. REINSPECTION: conductors are irrigation valve branch circuits to timer locations. 9. Install Generator fuel tank hazardous material signage, see Fire Marshal corrections. 10. Provide Fire Department access key for FD lock box. 11. COMPLETED Note: Security fencing & gates not installed TCO consideration forwarded to Building Official/BDM.

 02/04/2022TEMP. OCCUPANCYCURTIS L. JOHNSONPASS

 03/07/2022UNSPECIFIEDADAM KINGSLEYNOT REQUIREDMTG RE: NRCA FORMS3/7/2022 10:07:13 AM akingsley changed Inspection Date/Time from 03/07/2022 08:30 AM to 03/07/2022 4:30 PM 3/7/2022 4:34:51 PM Reviewed required energy compliance documents

 01/28/2022FIRE MARSHAL CLEARANCHRIS BOYDPASS1/28/2022 4:38:57 PM Ok to issue TCO. Need to provide keys for knox box, post an address and provide 2 NFPA 704 diamonds on generator visible from two opposite sides. Notified Travis with Slater Construction. 4/1/2022 10:57:24 AM Completed. Key are located in Knox box.

 04/01/2022**PERMIT FINALADAM KINGSLEYPASS3/30/2022 3:01:14 PM Previous corrections are completed except Outstanding fees showing unpaid. 4/1/2022 12:21:03 PM Updated final approval.