02/28/1850 | ENV HEALTH RELEASE | YVETTE CASTANON | | VOIDED (DAH 7/14/2020) | 7/14/2020 11:38:06 AM
Inspection voided by DAH.
|
|
12/15/2020 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PASS | | 12/15/2020 10:20:49 AM
Setbacks & pier footings also included. Ok for concrete placement.
Special inspection report for EOR structural observation & concrete compressive strength required.
2/17/2021 12:10:06 PM
SPECIAL INSPECTION RESULTS FOR REINFORCEMENT AND CONCRETE COMPRESSIVE STRENGTH ATTACHED.
ENGINEER OF RECORD OBSERVATION REPORT ATTACHED.
|
|
01/14/2021 | UNDER SLAB PLUMBING | ADAM KINGSLEY | PARTIAL | pm request | 1/14/2021 3:25:16 PM
Underslab cast DWV approved, ok to backfill. Underslab trap primers to be inspected at pre-slab.
|
|
02/12/2021 | UNDER SLAB PLUMBING | ADAM KINGSLEY | PASS | | 2/12/2021 9:03:45 AM
Trap primer piping verified.
2/17/2021 12:08:43 PM
UNDER SLAB DRAIN/WASTE PLAN REVISION ATTACHED. FIELD APPROVED.
|
|
02/16/2021 | PRE-SLAB | ADAM KINGSLEY | PARTIAL | | 2/12/2021 9:03:55 AM
akingsley changed Inspection Date/Time from 02/12/2021 08:30 AM to 02/16/2021 08:30 AM
2/16/2021 10:24:30 AM
akingsley changed Inspection Date/Time from 02/16/2021 10:00 AM to 02/16/2021 2:15 PM
2/16/2021 4:42:57 PM
Vehicle bays (construction pour #2 as noted on control joint plan) excluded, not ready. Remaining building interior approved for concrete placement.
2/17/2021 12:12:38 PM
BODY SCALE REINFORCEMENT ENGINEER REVISION ATTACHED
|
|
03/22/2021 | PRE-SLAB | ADAM KINGSLEY | PASS | | |
|
03/22/2021 | CMU 1ST POUR | ADAM KINGSLEY | FAIL | | 3/22/2021 5:30:22 PM
East and North elevation exterior walls not completed. Remaining exterior and interior walls inspected.
1. Type 2 walls horizontal reinforcement installed 16"oc. RFI from EOR missing stamp/signature. Provide written approval (sealed by EOR) or equal.
|
|
03/24/2021 | CMU 1ST POUR | ADAM KINGSLEY | FAIL | | 3/23/2021 4:24:19 PM
North elevation not completed at present. Inspected East elevation wall, pending the following
1. Type 2 walls horizontal reinforcement installed 16%34oc. RFI from EOR missing stamp/signature. Provide written approval (sealed by EOR) or equal
Reschedule next day.
3/23/2021 4:25:58 PM
akingsley changed Inspection Date/Time from 03/23/2021 to 03/24/2021
3/24/2021 4:43:24 PM
1. Extend reinforcement above lift to provide minimum required lap splice at the following locations:
-Vertical #5 and additional #5 jamb reinforcement at openings per detail 1/S1.3 located at staff corridor side door, all openings at north wall between autopsy and NW corner and several locations on interior walls.
-NW corner doubled vertical #5 per detail 2/S1.3
-single vertical #5 at opposing ends of control joints at several locations throughout.
Received engineer letter for change to type 2 wall, attached.
|
|
03/25/2021 | CMU 1ST POUR | ADAM KINGSLEY | PASS | | 3/25/2021 8:46:40 AM
Previous corrections are completed. Type 2 walls installed with horizontal #5 at 16" oc per engineer revision.
4/28/2021 12:23:07 PM
SPECIAL INSPECTION REPORTS ATTACHED (2) TWO FILES
|
|
04/14/2021 | MASONRY LIFTS | ADAM KINGSLEY | PARTIAL | 2nd of 4 lifts | 4/13/2021 3:31:55 PM
akingsley changed Inspection Date/Time from 04/13/2021 03:30 PM to 04/14/2021 1:00 PM
4/14/2021 3:05:28 PM
2nd lift of 4 -approved.
4/28/2021 12:09:59 PM
SPECIAL INSPECTION REPORT ATTACHED.
|
|
05/19/2021 | MASONRY LIFTS | ADAM KINGSLEY | PASS | 3rd of 4 lifts | 5/19/2021 8:21:06 PM
3rd of 4 lifts -approved.
|
|
05/26/2021 | MASONRY LIFTS | ADAM KINGSLEY | PASS | Last CMU Lift -PM Request | 5/26/2021 4:11:41 PM
4th/final lift for building -approved
|
|
07/19/2021 | ROUGH MECHANICAL | ADAM KINGSLEY | PARTIAL | Ductwork to be concealed | 7/19/2021 3:55:13 PM
Under roof ducts only -ok to insulate.
|
|
07/26/2021 | ROOF FRAME/SHEATHING | ADAM KINGSLEY | FAIL | | 7/27/2021 6:16:07 AM
Morgue roof frame
1. Provide written approval from engineer of record for
a) metal roof deck /ledger connection fix for parallel condition -welded steel tube filler;
b) incorrect beam length with welded shear tabs at entry staff corridor.
2. Roof deck puddle welds appear to have burnt through decking at several locations. Provide written approval from engineer of record or acceptance from special inspection.
Note: Partial inspection, structural framework only, roof nailing & mechanical curb/penetrations not complete at present.
Attached: engineer fix for retrofit beam embed & revision to mechanical curb/roof penetration
8/2/2021 6:12:55 AM
ITEM 1-a & 1-b CORRECTED. EOR LETTERS ATTACHED.
|
|
08/18/2021 | ROUGH PLUMBING | WOODY TOWNSEND | PARTIAL | PM REQUEST | 8/16/2021 4:24:22 AM
BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES)
8/19/2021 7:29:54 AM
All rough DWV top out test approved.
|
|
08/18/2021 | ROUGH FRAME | WOODY TOWNSEND | CANCELLED | PM REQUEST | 8/16/2021 4:24:06 AM
BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES)
|
|
08/19/2021 | PGE ELECTRIC TAG | WOODY TOWNSEND | PASS | PM REQUEST | 8/16/2021 4:23:50 AM
BUILDER SEEKING PARTIAL FOR WEST SIDE OF BUILDING (EVIDENCE FACILITY/OFFICES)
8/19/2021 7:30:09 AM
wtownsend changed Inspection Type from ROUGH ELECTRICAL to PGE ELECTRIC TAG
|
|
08/23/2021 | PGE ELECTRIC TAG | ADAM KINGSLEY | PASS | | 8/22/2021 9:39:58 PM
Contact Travis in am.
8/23/2021 4:00:24 PM
Retag 600A electric service, new address.
|
|
08/23/2021 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PARTIAL | | 8/23/2021 4:00:31 PM
Trash enclosure footings
|
|
08/25/2021 | ROUGH PLUMBING | ADAM KINGSLEY | PARTIAL | | 8/25/2021 2:40:33 PM
1. Hydronic HVAC piping not completed at present. Complete installation and test.
2. Provide separation of dissimilar materials at copper condensate drain pipes & steel supports.
Water supply (hot & cold cu) & cast iron DWV test & installation-approved. Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection.
8/25/2021 2:42:12 PM
1. Hydronic HVAC piping not completed at present. Complete installation and test.
2. Provide separation of dissimilar materials at copper condensate drain pipes & steel supports.
Water supply (hot & cold cu) & cast iron DWV test & installation-approved. Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection.
|
|
08/25/2021 | ROUGH MECHANICAL | ADAM KINGSLEY | PARTIAL | | 8/25/2021 2:42:20 PM
Concealed mechanical equipment/ductwork in wall cavities only -approved.
Ok to cover walls only. Roof deck/ceilings to remain exposed for inspection
1. Rooftop & ceiling space mechanical rough in not complete at present.
|
|
08/25/2021 | ROUGH FRAME | ADAM KINGSLEY | PARTIAL | | 8/25/2021 2:42:28 PM
Pending special inspection reports from roof frame inspection.
|
|
08/25/2021 | ROUGH ELECTRICAL | ADAM KINGSLEY | PARTIAL | | 8/25/2021 2:42:36 PM
Electrical components (raceways, device boxes, including fire alarm system) within concealed wall cavities only- approved. Ok to cover walls only.
All Circuit conductors & electric sub panel rough in not completed at present.
|
|
08/25/2021 | UNDERGROUND PLUMBING | ADAM KINGSLEY | PASS | | 8/25/2021 2:42:44 PM
Sand/oil separator & exterior drain pipe.
|
|
09/02/2021 | GAS PIPING | ADAM KINGSLEY | PARTIAL | | 9/2/2021 12:42:30 PM
Concealed piping & test -approved, ok to cover.
Remaining piping branches to boilers & water heaters not installed at present.
|
|
09/02/2021 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PARTIAL | | 9/2/2021 3:06:42 PM
GENERATOR PAD. CAST WITHOUT INSPECTION. VERIFIED VIA PHOTOGRAPHIC EVIDENCE.
PENDING SPECIAL INSPECTION REPORT
1/10/2022 2:48:08 PM
SPECIAL INSPECTION REPORTS ATTACHED. CONCRETE FC & REINFORCMENT
|
|
09/15/2021 | LIGHT STANDARD FTG | ADAM KINGSLEY | PARTIAL | | 9/15/2021 6:45:34 PM
Parking lot light standards, except two at front of building
|
|
09/20/2021 | TAG NATURAL GAS | ADAM KINGSLEY | PASS | | 9/20/2021 12:21:39 PM
Commercial - CNG.
|
|
10/26/2021 | ROOF FRAME/SHEATHING | ADAM KINGSLEY | PASS | | 10/26/2021 3:09:04 PM
PREVIOUS ROOF FRAME CORRECTIONS COMPLETED. ATTACHED SPECIAL INSPECTION FIELD WELDING & DECK PINNING REPORT.
|
|
11/04/2021 | T-BAR CEILING | ADAM KINGSLEY | PARTIAL | | 11/4/2021 6:10:14 PM
T-Bar inspection:
1. Missing seismic restraints throughout. Install per notes 5 & 6/A6.2
2. Locker room area not complete.
3. Missing light fixtures in Decomp room.
|
|
11/04/2021 | ROUGH FRAME | ADAM KINGSLEY | PASS | AM REQUEST | 11/4/2021 10:30:54 AM
akingsley changed Inspection Date/Time from 11/04/2021 09:00 AM to 11/04/2021 4:30 PM
11/4/2021 6:09:58 PM
akingsley changed Inspection Type from 4-WAY ROUGH FRAME to ROUGH FRAME
1/10/2022 2:51:02 PM
SPECIAL INSPECTION REPORT ATTACHED. GLASS MASONRY WINDOWS, POST INSTALLED ANCHORS AT STAIRS & GENERATOR
|
|
11/04/2021 | ROUGH MECHANICAL | ADAM KINGSLEY | PARTIAL | | 11/4/2021 6:18:51 PM
Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed.
Plumbing- Boilers and equipment room not completed.
Framing-pass
Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry.
Note: Need special inspection reports for generator foundation pad concrete compressive strength
|
|
11/04/2021 | ROUGH PLUMBING | ADAM KINGSLEY | PARTIAL | | 11/4/2021 6:18:59 PM
Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed.
Plumbing- Boilers and equipment room not completed.
Framing-pass
Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry.
Note: Need special inspection reports for generator foundation pad concrete compressive strength
|
|
11/04/2021 | ROUGH ELECTRICAL | ADAM KINGSLEY | PARTIAL | | 11/4/2021 6:19:07 PM
Mechanical-Previous areas completed. Complete duct/register connections in t-bar area. Boilers & equipment room not completed.
Plumbing- Boilers and equipment room not completed.
Framing-pass
Electrical- Previous areas completed. Need to complete generator/t-switch inspection. Complete t-bar electrical, missing lights fixtures in Decomp & Laundry.
Note: Need special inspection reports for generator foundation pad concrete compressive strength
|
|
11/10/2021 | SHOWER PAN/TUB TEST | ADAM KINGSLEY | PASS | PM REQUEST | 11/10/2021 1:42:43 PM
Two (2) accessible shower pans
|
|
11/10/2021 | T-BAR CEILING | ADAM KINGSLEY | PASS | | 11/10/2021 1:43:02 PM
Previous T-bar ceiling corrections completed.
|
|
01/03/2022 | ROUGH PLUMBING | ADAM KINGSLEY | PASS | | 1/3/2022 1:20:45 PM
Previous items addressed/completed.
|
|
01/03/2022 | ROUGH MECHANICAL | ADAM KINGSLEY | PASS | | 1/3/2022 1:20:53 PM
Previous items addressed/completed.
|
|
01/03/2022 | ROUGH ELECTRICAL | ADAM KINGSLEY | PASS | | 1/3/2022 1:21:01 PM
Previous items addressed/completed.
1/10/2022 2:49:17 PM
SPECIAL INSPECTION REPORT ATTACHED FOR GENERATOR POST INSTALLED ANCHORS.
|
|
11/04/2021 | LIGHT STANDARD FTG | ADAM KINGSLEY | PASS | | 11/4/2021 6:10:06 PM
Remaining parking lot light standards -approved
1/10/2022 2:47:16 PM
SPECIAL INSPECTION REPORT -REINFORCEMENT. ATTACHED
|
|
02/28/1850 | NPDES | PWROADS | | VOIDED (CJ 1/26/2022) | 1/26/2022 11:46:17 AM
Inspection voided by CJ.
|
|
02/28/1850 | LAND DEV FINAL | PWLANDDEV | | VOIDED (CJ 1/26/2022) | 1/26/2022 11:47:49 AM
Inspection voided by CJ.
|
|
01/27/2022 | **PERMIT FINAL | ADAM KINGSLEY | FAIL | | 1/27/2022 6:53:05 PM
1. Provide knee protection for sink drain pipes at the following sinks: Evidence processing, Login processing (morgue), break room, grossing lab and forensic lab.
2. Provide GFCI protection for receptacles within 6' of sink at Decomp workbench (two receptacles nearest sink).
3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear.
4. Provide Fire Marshal Final clearance and final permit B20-2402 (fire alarm system).
5. Provide energy compliance documents for required acceptance tests:
NRCA-ENV-02-F
NRCA-LTI-02 & 04-A
NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A
Exterior disabled access compliance, parking & egress elements not included and will need to be inspected prior to TCO consideration.
Items 1-4 require correction prior to TCO consideration.
|
|
01/31/2022 | **PERMIT FINAL | ADAM KINGSLEY | FAIL | | 1/31/2022 4:29:38 PM
Previous corrections are completed except:
ALK 1/27/2022 6:53:05 PM
1. Provide knee protection for sink drain pipes at the following sinks: Evidence processing, Login processing (morgue), break room, grossing lab and forensic lab.
2. COMPLETED
3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear.
4. Provide Fire Marshal Final clearance. REINSPECTION: FM provided partial clearance.
5. Provide energy compliance documents for required acceptance tests:
NRCA-ENV-02-F
NRCA-LTI-02 & 04-A
NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A
EXTERIOR REINSPECTION (no access to interior)
6. Provide posted address number(s) on the building.
7. Mini split disconnect fuses missing at West elevation ground level unit.
8. Exposed conductors at building SW corner. Terminate conductors in a listed box, conduit, device or equal.
9. Install Generator fuel tank hazardous material signage, see Fire Marshal corrections.
10. Provide Fire Department access key for FD lock box.
11. Remove construction debris from public areas or job site or equal.
Note: Security fencing & gates not installed at present.
|
|
02/02/2022 | **PERMIT FINAL | ADAM KINGSLEY | FAIL | | 2/2/2022 6:11:55 PM
Previous corrections are completed except:
1. COMPLETED
2. COMPLETED
3. Provide permanent marking/label indicating maximum available fault current supplied and calculation date at main electric service/switch gear.
4. Provide Fire Marshal Final clearance. REINSPECTION: FM provided partial clearance.
5. Provide energy compliance documents for required acceptance tests:
NRCA-ENV-02-F
NRCA-LTI-02 & 04-A
NRCA-MCH-02, 05, 07, 08, 10, 11, 16, 18, 19-A
6. COMPLETED
7. N/A COMPLETED
8. Exposed conductors at building SW corner. REINSPECTION: conductors are irrigation valve branch circuits to timer locations.
9. Install Generator fuel tank hazardous material signage, see Fire Marshal corrections.
10. Provide Fire Department access key for FD lock box.
11. COMPLETED
Note: Security fencing & gates not installed
TCO consideration forwarded to Building Official/BDM.
|
|
02/04/2022 | TEMP. OCCUPANCY | CURTIS L. JOHNSON | PASS | | |
|
03/07/2022 | UNSPECIFIED | ADAM KINGSLEY | NOT REQUIRED | MTG RE: NRCA FORMS | 3/7/2022 10:07:13 AM
akingsley changed Inspection Date/Time from 03/07/2022 08:30 AM to 03/07/2022 4:30 PM
3/7/2022 4:34:51 PM
Reviewed required energy compliance documents
|
|
01/28/2022 | FIRE MARSHAL CLEARAN | CHRIS BOYD | PASS | | 1/28/2022 4:38:57 PM
Ok to issue TCO. Need to provide keys for knox box, post an address and provide 2 NFPA 704 diamonds on generator visible from two opposite sides. Notified Travis with Slater Construction.
4/1/2022 10:57:24 AM
Completed. Key are located in Knox box.
|
|
04/01/2022 | **PERMIT FINAL | ADAM KINGSLEY | PASS | | 3/30/2022 3:01:14 PM
Previous corrections are completed except
Outstanding fees showing unpaid.
4/1/2022 12:21:03 PM
Updated final approval.
|
|