03/02/2020 | ENV HEALTH RELEASE | PAUL THAO | PASS | | 3/2/2020 9:54:36 AM
Septic setbacks met approved.
|
|
04/28/2020 | FOUNDATION/FOOTINGS | WOODY TOWNSEND | PASS | 041283-01 - Scheduled by IVR. | |
|
05/26/2020 | UNDERFLOOR PLUMBING | ADAM KINGSLEY | PASS | 042082-01 - Scheduled by IVR. | 5/26/2020 10:40:38 AM
Underfloor gas pipe/ test included
|
|
05/26/2020 | UNDERFLOOR FRAMING | ADAM KINGSLEY | PASS | | 5/26/2020 10:40:44 AM
Shear transfer also included
|
|
06/17/2020 | ROOF NAIL | WOODY TOWNSEND | PASS | | |
|
06/17/2020 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PASS | | |
|
07/14/2020 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | PASS | 043709-01 - Scheduled by IVR. | |
|
| ROUGH PLUMBING | ADAM KINGSLEY | | VOIDED (ALK 9/30/2020) | 9/30/2020 6:34:55 AM
Inspection voided by ALK. Most recent remarks follow: 046067-01 - Scheduled by IVR.
|
|
| ROUGH MECHANICAL | ADAM KINGSLEY | | VOIDED (ALK 9/30/2020) | 9/30/2020 6:35:09 AM
Inspection voided by ALK. Most recent remarks follow: 046067-02 - Scheduled by IVR.
|
|
09/30/2020 | **PERMIT FINAL | ADAM KINGSLEY | FAIL | 046067-03 - Scheduled by IVR. | 9/30/2020 3:20:28 PM
akingsley changed Inspection Type from UNSPECIFIED to **PERMIT FINAL
9/30/2020 3:23:13 PM
1. Provide minimum one luminaire controlled by vacancy sensor or equal.
|
|
10/20/2020 | **PERMIT FINAL | ADAM KINGSLEY | PASS | 046668-01 - Scheduled by IVR. | 10/20/2020 1:32:54 PM
Previous corrections are completed
|
|