02/28/1850 | NPDES | PWROADS | | VOIDED (SC 11/25/2019) | 11/25/2019 2:03:57 PM
Inspection voided by SC.
|
|
| ENV HEALTH RELEASE | YVETTE CASTANON | PASS | | |
|
02/20/2020 | FOUNDATION/FOOTINGS | PHILLIP MYERS | PASS | 039282-01 - Scheduled by IVR. | 2/20/2020 10:26:25 AM
All footings ok suggest Ufer ground, for future panel
|
|
03/13/2020 | PRE-SLAB | ADAM KINGSLEY | PASS | 040002-01 - Scheduled by IVR. | |
|
05/07/2020 | ROUGH FRAME | ADAM KINGSLEY | PASS | 041560-01 - Scheduled by IVR. | |
|
05/07/2020 | UNDERGROUND ELECTRIC | ADAM KINGSLEY | PASS | | 5/7/2020 1:53:42 PM
Garage to pole/meter
|
|
05/07/2020 | ROOF NAIL | ADAM KINGSLEY | PASS | | |
|
05/07/2020 | SHEARWALL/B.W.P.-EXT | ADAM KINGSLEY | PASS | | |
|
05/07/2020 | ROUGH ELECTRICAL | ADAM KINGSLEY | FAIL | | 5/7/2020 1:54:02 PM
1. Grounding electrode conductor not installed/ connected to eufer ground. Complete installation.
2. Neutral feeder/ conductors bonded to equipment grounding feeder/ conductors at garage sub panel. Isolate neutral terminal block, install separate grounding terminal block & relocate grounding conductors.
3. Building not weather tight.
Ok to proceed and follow up at next inspection.
|
|
07/09/2020 | CAL FIRE FINAL INSPE | JOHN GADDIE | PASS | | 7/9/2020 3:54:02 PM
OK to Final
|
|
07/15/2020 | **PERMIT FINAL | RICHARD PRATT | PASS | 043760-01 MSG! -Msg! Scheduled by IVR. | 7/15/2020 6:10:44 AM
rpratt changed Inspection Date/Time from 07/15/2020 08:00 AM to 07/15/2020 2:00 PM
7/15/2020 7:14:22 PM
Garage Final Approved
|
|