02/28/1850 | NPDES | QUENTIN CARTER | | VOIDED (SLN 11/18/2019) | 11/18/2019 1:51:19 PM
Inspection voided by SLN.
|
|
11/27/2019 | ENV HEALTH RELEASE | VANCE SEVERIN | PASS | | |
|
01/09/2020 | FOUNDATION/FOOTINGS | SCOTT YOUNG | PASS | 037850-01 - Scheduled by IVR. | |
|
01/22/2020 | PRE-SLAB | ADAM KINGSLEY | PASS | AM REQUEST | 1/22/2020 2:11:55 PM
Basement & garage.
Underground plumbing included (stacks & building drain)
|
|
02/03/2020 | PIER/COLUMN FOOTINGS | ADAM KINGSLEY | PASS | | |
|
02/04/2020 | UNDERFLOOR PLUMBING | SCOTT YOUNG | PASS | 038668-01 - Scheduled by IVR. | |
|
02/20/2020 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | PASS | 039243-01 - Scheduled by IVR. | 2/20/2020 2:15:25 PM
Looked at interior/exterior shearwall and roof nail.
|
|
03/13/2020 | FIRE SPRINKLERS | PHILLIP MYERS | PASS | 040001-02 - Scheduled by IVR. | |
|
03/13/2020 | 4-WAY ROUGH FRAME | PHILLIP MYERS | PASS | 040001-01 - Scheduled by IVR. | |
|
04/16/2020 | SHOWER PAN/TUB TEST | ADAM KINGSLEY | PASS | 040960-01 - Scheduled by IVR. | 4/16/2020 6:26:54 AM
akingsley changed Inspection Date/Time from 04/16/2020 08:00 AM to 04/16/2020 1:00 PM
4/16/2020 1:50:15 PM
Note: KERDI system drained by tile setter prior to inspection. Visible water line remnant indicates it was watertight.
|
|
07/06/2020 | GAS TEST | ADAM KINGSLEY | PASS | 043432-01 - Scheduled by IVR. | 7/6/2020 11:32:55 AM
Whole system.
|
|
07/06/2020 | UNDERGROUND GAS | ADAM KINGSLEY | FAIL | | 7/6/2020 11:33:02 AM
1. Underground pipe covered prior to inspection. Expose all pipe joints and recall inspection.
Gas test passed.
|
|
07/07/2020 | GAS PIPING | SCOTT YOUNG | PASS | 043510-01 - Scheduled by IVR. | |
|
08/05/2020 | CAL FIRE FINAL INSPE | CHRIS BOYD | PASS | | 8/5/2020 11:35:36 AM
Ok to final
|
|
08/07/2020 | **PERMIT FINAL | SCOTT YOUNG | PASS | 044522-01 - Scheduled by IVR. | |
|