12/04/2019 | FOUNDATION/FOOTINGS | PHILLIP MYERS | PASS | 036719-01 MSG! -Msg! Scheduled by IVR. | |
|
12/10/2019 | PIER/COLUMN FOOTINGS | PHILLIP MYERS | PASS | 036905-01 MSG! -Msg! Scheduled by IVR. | 12/10/2019 11:26:03 AM
The Inspection today is for the firewall caissons for grade beams between each of the new transformers. These caissons and grade beams are being poured in 2 lifts. Engineer of record is aware of cold joint and is going to provide wet stamped letter verifying this condition.
|
|
01/17/2020 | FIREWALL/OCCUP SEP | PHILLIP MYERS | PASS | am request | 1/17/2020 8:35:15 AM
This Inspection is for the steel prior to the monolithic concrete placement of the grade beams.
|
|
02/12/2020 | MASONRY GROUT | PHILLIP MYERS | PASS | 038968-01 MSG! -Msg! Scheduled by IVR. | 2/12/2020 10:42:58 AM
4th lift CMU prior to concrete placement
|
|
02/20/2020 | MASONRY GROUT | PHILLIP MYERS | PASS | AM REQUEST -- 530-227-0478 | 2/19/2020 2:25:00 PM
SECURITY GATE PLEASE CALL -- 530-227-0478
2/20/2020 9:06:24 AM
Lift #8 ok to grout.
|
|
02/25/2020 | MASONRY GROUT | SCOTT YOUNG | PASS | REQ AM | 2/25/2020 1:53:00 PM
Top lift completed #10 , grouted.
|
|
05/17/2023 | **PERMIT FINAL | SCOTT YOUNG | FAIL | 066667-01 MSG! -Msg! Scheduled by IVR. | 5/18/2023 6:16:19 AM
Have approved stamped plans from Butte County onsite.
NPDES AND Public works sign off.
cal fire sign off required
|
|