| NPDES | QUENTIN CARTER | | | |
|
| CAL FIRE FINAL INSPE | CHRIS BOYD | | | |
|
| IMPACT FEES DUE | PERMIT CENTER | | | |
|
11/05/2019 | FOUNDATION/FOOTINGS | SCOTT YOUNG | PASS | | |
|
11/21/2019 | UNDERFLOOR PLUMBING | SCOTT YOUNG | PASS | | |
|
01/22/2020 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PARTIAL | | 1/22/2020 3:24:05 PM
Exterior shear nail only. Shear transfer and hardware not ready.
|
|
01/22/2020 | ROOF NAIL | WOODY TOWNSEND | FAIL | | 1/22/2020 3:25:49 PM
1. Expose roof nail at drag and truss blocking. Roof nail covered without inspection.
2. Clarify locations of truss blocking per A9/3 detail. Blocking not in at this time.
|
|
01/28/2020 | SHEARWALL/B.W.P.-EXT | PHILLIP MYERS | PASS | | |
|
02/18/2020 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | FAIL | | 2/18/2020 2:40:58 PM
1. Provide 3300 com whole house fan per energy calls or equal.
2. Provide listed CSST nail protection at kitchen top plate penetrations (2 locations)
3. Provide interconnected smoke alarm circuit & device box outside master bedroom.
4. Provide mid story support for vertical PVC DWV pipe.
Ok to insulate.
|
|
02/20/2020 | 4-WAY ROUGH FRAME | PHILLIP MYERS | PASS | | |
|
02/25/2020 | UNDERGROUND GAS | SCOTT YOUNG | PASS | | |
|
02/25/2020 | PGE ELECTRIC TAG | SCOTT YOUNG | FAIL | | 2/25/2020 3:28:30 PM
Need to have listed waterproof box with GFCI outlet on a 20 amp breaker. Mounted below main panel.
|
|
02/26/2020 | PGE ELECTRIC TAG | ADAM KINGSLEY | CANCELLED | | 2/26/2020 3:28:28 PM
Cancelled by Contractor
|
|
02/28/2020 | PGE ELECTRIC TAG | PHILLIP MYERS | PASS | | |
|
04/13/2020 | **PERMIT FINAL | ADAM KINGSLEY | FAIL | | 4/13/2020 6:20:56 AM
akingsley changed Inspection Date/Time from 04/13/2020 08:00 AM to 04/13/2020 1:30 PM
4/13/2020 3:09:01 PM
1. Provide CalFire & Environmental Health Final approvals.
2. Provide insulation at water heater hot & cold water supply pipes.
3. Provide min one luminaire controlled by vacancy sensor or equal at bathrooms.
|
|
04/14/2020 | ENV HEALTH RELEASE | DARREN JONES | PASS | ok to release | |
|
04/15/2020 | **PERMIT FINAL | ADAM KINGSLEY | PASS | | 4/15/2020 6:11:20 AM
akingsley changed Inspection Date/Time from 04/15/2020 08:00 AM to 04/15/2020 12:30 PM
|
|