| NPDES | QUENTIN CARTER | | | |
|
07/22/2019 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | FAIL | | 7/22/2019 8:10:50 AM
INSPECTION ADDED PER BDM, PRIOR TO ISSUANCE.
7/22/2019 11:12:47 AM
1. Interior pier footings undersized per approved plans, FT3 Installed; FT4 required. Provide min 24" sq x 18"deep w/ 4 #4 ew or equal.
2. Missing (3) FT4 spread footings at back wall per plans. Provide required footings or equal.
Setbacks & HDs verified, no approval until permit is issued.
|
|
07/24/2019 | UFER GROUND | ADAM KINGSLEY | PASS | 031416-03 MSG! -Msg! Scheduled by IVR. | |
|
07/24/2019 | SETBACKS | ADAM KINGSLEY | PASS | 031416-02 - Scheduled by IVR. | |
|
07/24/2019 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PASS | 031416-01 - Scheduled by IVR. | 7/24/2019 2:58:25 PM
Previous corrections are completed. Pier footings included
|
|
07/29/2019 | PRE-SLAB | ADAM KINGSLEY | PASS | 031578-01 - Scheduled by IVR. | |
|
08/01/2019 | UNDERFLOOR PLUMBING | MIKE KNIGHT | PASS | 031783-02 - Scheduled by IVR. | 8/1/2019 4:02:46 PM
Covered without inspection but appears to be plumbed correctly from the limited view from the crawl space.
|
|
08/01/2019 | UNDERFLOOR FRAMING | MIKE KNIGHT | PASS | 031783-01 MSG! -Msg! Scheduled by IVR. | 8/1/2019 4:02:51 PM
Covered without inspection but I was able to verify floor frame is consistent with plans viewing from underfloor area.
|
|
08/12/2019 | SHEARWALL/B.W.P.-EXT | ADAM KINGSLEY | PASS | 032168-01 - Scheduled by IVR. | 8/12/2019 11:38:52 AM
Interior SW included
|
|
08/12/2019 | ROOF NAIL | ADAM KINGSLEY | PASS | | |
|
09/04/2019 | PGE ELECTRIC TAG | ADAM KINGSLEY | PASS | | |
|
09/04/2019 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | FAIL | | 9/4/2019 4:00:33 PM
1. Fire Sprinkler permit & plans not provided.
2. Underfloor area exposed. Provide rat proofing (1/4" wire mesh or equal) at bathtub drain and lavatory drain in master bathroom.
3. Transfer switch roughed in. Separate permit required for Generator & PV system.
|
|
09/06/2019 | 4-WAY ROUGH FRAME | SCOTT YOUNG | PASS | | 9/6/2019 12:46:49 PM
Corrections addressed
|
|
11/26/2019 | **PERMIT FINAL | MIKE KNIGHT | PARTIAL | | 11/26/2019 3:38:32 PM
1. Install address numbers on house. 2. Need Cal Fire and Environmental Health approvals. Need to verify HERS as complete.
|
|
11/26/2019 | PGE GAS TAG | MIKE KNIGHT | PASS | | |
|
| ENV HEALTH RELEASE | KATTY HERNANDEZ | PASS | | 7/22/2019 4:43:06 PM
7/22/19 - hold for septic final, see notes in review YC
12/2/2019 11:15:06 AM
SEPTIC FINAL COMPLETE.
|
|
12/03/2019 | CAL FIRE FINAL INSPE | CHRIS BOYD | PASS | | 12/3/2019 9:14:11 AM
For John Gaddie. Ok to Final
|
|
12/03/2019 | **PERMIT FINAL | MIKE KNIGHT | PASS | | 12/3/2019 4:33:09 PM
All corrections addressed.
|
|