| NPDES | QUENTIN CARTER | | | |
|
07/08/2019 | PGE ELECTRIC TAG | ADAM KINGSLEY | PASS | 030708-01 - Scheduled by IVR. | 7/8/2019 11:03:10 AM
Construction power approved
|
|
07/10/2019 | FOUNDATION/FOOTINGS | WOODY TOWNSEND | FAIL | | 7/8/2019 10:16:27 AM
AFTERNOON REQUEST
7/10/2019 4:22:38 PM
wtownsend changed Inspection Type from 4-WAY ROUGH FRAME to FOUNDATION/FOOTINGS
7/15/2019 10:51:32 AM
1. Provide footings and reinforcement per plan.
2. Provide engineers approval for two pour.
3. correct flat vent at water closet vent.
4. Provide 10'' head test.
|
|
07/15/2019 | FOUNDATION/FOOTINGS | WOODY TOWNSEND | PASS | | |
|
07/15/2019 | UNDER SLAB PLUMBING | WOODY TOWNSEND | PASS | | |
|
07/17/2019 | PRE-SLAB | WOODY TOWNSEND | PASS | PM REQUESTED | |
|
07/22/2019 | PIER/COLUMN FOOTINGS | ADAM KINGSLEY | PASS | 031304-01 - Scheduled by IVR. | 7/22/2019 9:48:09 AM
Porch footings
|
|
07/23/2019 | UNDERGROUND GAS | WOODY TOWNSEND | PASS | | 7/23/2019 5:20:22 PM
Pipe and test/ meter to house.
|
|
07/23/2019 | UNDERGROUND ELECTRIC | WOODY TOWNSEND | VOID | | |
|
07/23/2019 | UNDERGROUND CONDUIT | WOODY TOWNSEND | PASS | | 7/23/2019 5:20:35 PM
House to pole and pole to shop.
|
|
07/24/2019 | UNDERGROUND WATER PI | ADAM KINGSLEY | PASS | AM REQUEST | 7/24/2019 2:58:04 PM
Well to SFD, electrical circuit included
|
|
08/21/2019 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PASS | 032597-01 - Scheduled by IVR. | |
|
08/21/2019 | ROOF NAIL | WOODY TOWNSEND | PASS | | |
|
08/26/2019 | ROUGH ELECTRICAL | WOODY TOWNSEND | PARTIAL | 032559-01 - Scheduled by IVR. | 8/26/2019 12:57:01 PM
wtownsend changed Inspection Type from PGE ELECTRIC TAG to ROUGH ELECTRICAL
8/26/2019 2:39:18 PM
Rough electrical and frame at front porch lid okay to cover.
|
|
09/05/2019 | GAS TEST | SCOTT YOUNG | PASS | | |
|
09/05/2019 | 4-WAY ROUGH FRAME | SCOTT YOUNG | CANCELLED | | 9/5/2019 5:08:41 PM
Not ready.
|
|
09/16/2019 | FIRE SPRINKLERS | ADAM KINGSLEY | VOID | PM Request | 9/16/2019 10:29:04 AM
Inspection added to permit B19-2751.
|
|
09/16/2019 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | FAIL | PM Request | 9/16/2019 10:29:15 AM
1. Wiring method (NM-sheathed cable) for kitchen island not listed for outside use (under slab in conduit). Provide listed conductors, method or equal.
Ok to proceed and follow up at next inspection.
|
|
09/17/2019 | CAL FIRE FINAL INSPE | CHRIS BOYD | PASS | | 9/17/2019 4:09:03 PM
Ok to final
|
|
09/25/2019 | INSULATION (WALL) | MIKE KNIGHT | NOT REQUIRED | | |
|
09/25/2019 | INSULATION (ROOF) | MIKE KNIGHT | NOT REQUIRED | AM Request | |
|
10/09/2019 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | PASS | | 10/9/2019 11:13:39 AM
Previous corrections are completed
|
|
10/09/2019 | PGE GAS TAG | ADAM KINGSLEY | PASS | | 10/9/2019 11:14:31 AM
House test included
|
|
11/15/2019 | ENV HEALTH RELEASE | DARREN JONES | PASS | ok to rls | 11/15/2019 4:14:25 PM
septic and well finalled
|
|
12/04/2019 | **PERMIT FINAL | MIKE KNIGHT | PASS | | 12/4/2019 11:53:11 AM
Dishwasher not set, may be added in future.
12/6/2019 3:17:13 PM
Hazard Tree Removal Program Inspection access for provided, will add to code case.
|
|