10/04/2018 | UNDERGROUND ELECTRIC | MIKE GENNA | PASS | 022908-01 - Scheduled by IVR. | |
|
10/04/2018 | GAS PIPING | MIKE GENNA | PASS | 022908-02 - Scheduled by IVR. | |
|
10/04/2018 | SEWER(PIPE/TEST/TAP) | MIKE GENNA | PASS | 022908-03 - Scheduled by IVR. | |
|
10/04/2018 | UNDERGROUND WATER PI | MIKE GENNA | PASS | 022908-04 - Scheduled by IVR. | |
|
10/04/2018 | PGE ELECTRIC TAG | MIKE GENNA | PASS | | |
|
10/09/2018 | PERM FOUNDATION | ADAM KINGSLEY | PARTIAL | 023074-01 - Scheduled by IVR. | 10/9/2018 12:05:20 PM
Blocking/xi2 foundation installation not completed. Utility side and marriage line only, approved. Frame blocking on access side is not completed.
10/9/2018 2:14:46 PM
setbacks approved.
|
|
10/15/2018 | BLOCKING/UNDERPINNIN | SCOTT YOUNG | PASS | 023239-01 - Scheduled by IVR. | |
|
10/15/2018 | PERM FOUNDATION | SCOTT YOUNG | PASS | 023239-02 - Scheduled by IVR. | |
|
10/15/2018 | MANOMETER TEST | SCOTT YOUNG | PASS | 023239-03 - Scheduled by IVR. | |
|
10/15/2018 | CONTINUITY TEST | SCOTT YOUNG | FAIL | 023239-04 - Scheduled by IVR. | 10/15/2018 4:42:06 PM
They were not set up continuity test
10/16/2018 7:52:43 AM
They were not set up continuity test
|
|
11/09/2018 | CONTINUITY TEST | LARRY AKERS | PASS | 023922-01 - Scheduled by IVR. | 11/9/2018 4:02:26 PM
Continuity, skirling and landings approved
|
|
11/09/2018 | SKIRTING & STEPS | LARRY AKERS | | 023922-02 - Scheduled by IVR. | |
|
11/30/2018 | **PERMIT FINAL | LARRY AKERS | FAIL | 024378-01 - Scheduled by IVR. | 11/30/2018 9:25:25 AM
1) need 433A and county health sign off.
|
|
| ENV HEALTH RELEASE | DARREN JONES | PASS | ok to rls 9/14/2018 | |
|
02/28/1850 | NPDES | | | VOIDED (TOM BLIXT 8/30/2018) | |
|
01/01/2019 | CAL FIRE FINAL INSPE | CHRIS BOYD | PASS | | 12/6/2018 2:16:25 PM
Ok to final.
|
|
| 433A | PERMIT CENTER | PASS | | |
|