07/10/2018 | UNDER SLAB PLUMBING | ADAM KINGSLEY | PASS | | 7/10/2018 12:09:00 PM
Inspected and approved at foundation inspection.
|
|
07/03/2018 | FOUNDATION/FOOTINGS | ADAM KINGSLEY | PARTIAL | 020371-01 - Scheduled by IVR. | 7/3/2018 2:08:10 PM
Setbacks and pier footings approved.
Footing approval pending EOR written approval for slab ties installed without bottom hooks and NW corner change (SW moved inches to accommodate corner being removed).
|
|
09/26/2018 | ROOF NAIL | MIKE GENNA | PASS | 022686-01 MSG! -Msg! Scheduled by IVR. | |
|
12/04/2018 | SHEARWALL/B.W.P.-EXT | ADAM KINGSLEY | FAIL | 024412-01 MSG! -Msg! Scheduled by IVR. | 12/4/2018 10:41:35 AM
1. CS16 straps and blocking not installed at perforated shearwalls per Detail SD/6; plate height change per detail 16/SD1 and 13/SD1. Install required hardware or provide written approval from engineer of record.
2. HDU2/threaded rods not installed at south facing Shearwall per plans. Install required hardware or provide written approval from engineer of record. (Ok to follow up with item #2 at 4way inspection)
|
|
12/10/2018 | SHEARWALL/B.W.P.-EXT | ADAM KINGSLEY | PARTIAL | 024528-01 - Scheduled by IVR. | 12/10/2018 11:49:28 AM
Previous corrections are completed except special inspection report for epoxied AB's or equal. See previous inspection corrections. Ok to proceed and follow up at next inspection.
|
|
12/06/2018 | SHEARWALL/B.W.P.-EXT | LARRY AKERS | FAIL | 024467-01 MSG! -Msg! Scheduled by IVR. | 12/6/2018 12:56:16 PM
1) missing straps check detail for shear walls 6sn with openings 2 places, need straps top and bottom
2) need special inspection of threaded rods
|
|
12/18/2018 | 4-WAY ROUGH FRAME | ADAM KINGSLEY | PARTIAL | 024786-01 MSG! -Msg! Scheduled by IVR. | 12/18/2018 12:35:41 PM
1. NM sheathed cable installed under slab in conduit at bar island, wiring method not listed for installation outside the building or wet location. Provide listed wiring method for application or equal.
Ok to proceed, follow up at next inspection.
|
|
01/31/2019 | STUCCO (LATH) | LARRY AKERS | PASS | 025908-01 MSG! -Msg! Scheduled by IVR. | |
|
03/12/2019 | PLUMBING FINAL | SCOTT YOUNG | PASS | 026857-01 MSG! -Msg! Scheduled by IVR. | |
|
04/23/2019 | **PERMIT FINAL | LARRY AKERS | PASS | 028016-01 MSG! -Msg! Scheduled by IVR. | |
|
12/18/2018 | SHEARWALL/B.W.P.-EXT | ADAM KINGSLEY | PASS | | 12/18/2018 4:54:05 PM
Received EOR epoxied anchor letter, attached to permit.
|
|
| ENV HEALTH RELEASE | DARREN JONES | | | |
|
| NPDES | | | Chapter 50 area | |
|
07/10/2018 | PRE-SLAB | ADAM KINGSLEY | PASS | | 7/9/2018 2:56:12 PM
AM REQUESTED BRETT 624.3805
|
|