04/28/2024
10:15 AM

Butte County
Department of Development Services

Main: 530.552.3700
Automated Inspection Phone Line: 530.538.4365
Online Inspection Scheduling / Payments / Renewals:
ButteCounty.net/DDS

 
Permit No. B16-2286 Permit Type   RESIDENTIAL Site Address   77 TIPSOO PEAK
BERRY CREEK, CA 95916
Applied   10/13/2016 Applicant   SCHEUERMANN, JANE
Approved   12/16/2016 Owner   HOLMES STEVEN L & POTTS LORI A
Issued   01/03/2017 Contractor   J A D BUILT GENERAL CONSTRUCTION
Parent Permit No.   Description   NSF (1846) GAR (576) COV DECK (474) OPEN AREA (476)
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 12/14/2017SHEARWALL/B.W.P.-EXTJERRY RISENHOOVERFAIL12/14/2017 1:46:26 PM Several items are not completed Inspection was stoped An engineers letter will need to be provided by the contractor for door location change at garage wall, location of window placement and proposed inclosed deck where owner plans to make a screened area versus what the plans specified as a complete shear wall. All hold downs, squash blocking needs to be completed. Re inspection required.

 12/07/2018ROOF NAILADAM KINGSLEYFAIL12/7/2018 3:52:10 PM Roof nail 1. Roofing material applied/ covered without roof nail drag truss inspection. Provide access to work for inspection or written verification roof is installed per design by engineer of record.

ENV HEALTH RELEASEDARREN JONESPASSok to release

 03/21/2017FOUNDATION/FOOTINGSSCOTT YOUNGPASS

 04/11/2019UNDERFLOOR FRAMINGSCOTT YOUNGFAIL4/11/2019 3:16:20 PM Shear was not done, he is still working on hold downs and had not gotten to shearwall. I was able to verify underfloor holddowns, he will be connecting all thread to bring through sub floor framing.ok to take pictures after all thread is placed to shear underfloor pony wall. I've asked him to mark and number each one and take pictures.

 04/18/2019UNDERFLOOR FRAMINGSCOTT YOUNGPASS027958-01 - Scheduled by IVR.4/18/2019 1:45:11 PM Verified all Simpson holdowns and straps underfloor through 1st floor frame, Ok to shear.

 09/05/20184-WAY ROUGH FRAMEADAM KINGSLEYFAIL8/29/2018 2:39:37 PM APPLICANTS HAVE NEW CONTRACTOR AND NEED HELP WITH INSPECTION INFORMATION SCHEDULING 4WAY SO THEY CAN GET INFORMATION ON PERMITS. B16-2286 B16-2287 9/5/2018 7:38:20 AM Project is not ready for 4-way inspection. electrical & mechanical rough in not completed. The following inspections are not completed/passed and required prior to 4-way inspection: -Exterior Shearwall -Roof Nail -Underfloor framing, mechanical, plumbing and shear transfer

 01/17/2019ROOF NAILADAM KINGSLEYPASS1/17/2019 2:55:00 PM As-built, see attached EOR inspection letter.

 01/31/2019STUCCO (LATH)ADAM KINGSLEYPASS

 12/06/2018SHEARWALL/B.W.P.-EXTADAM KINGSLEYFAIL12/7/2018 3:59:16 PM Exterior Shearwall 1. Provide written approval/ fix for penetration in west shearwall (pedestrian door added) by engineer of record or equal. 2. Provide written approval/ fix for window added in south garage shearwall from engineer of record. Window king stud covers AB/ HD not installed. 3. Exterior OSB sheathing shows weathering and delamination. Provide structural observation for condition of OSB sheathing from engineer of record.

 12/06/2018UNDERFLOOR FRAMINGADAM KINGSLEYFAIL12/7/2018 3:50:21 PM Underfloor Plumbing 1. ABS DWV pipe test not provided. Ok to test complete system at 4-way inspection. Underfloor framing 1. Blocking not provided at interior shearwall per detail 4/SD4. Provide required blocking or provide written approval from engineer of record. 2. TJI I joist substituted for LVL at interior shearwall. Provide LVL per detail 4/SD4 or written approval from engineer of record. 3. Anchor bolt missing nuts and 3”x3” plates at several locations. Provide required nuts and plates. 4. Plans indicate HDU2’s & HDU4’s to be installed, several locations substituted for other models of HD devices. Provide written approval from the engineer of record for design alteration or equal. 5. Threaded rod shear transfer not installed at cripple wall HD locations per plans. Provide shear transfer per plans or written approval from engineer of record or equa. 6. Squash blocking missing from posts, built up studs at several locations. Provide positive full depth blocking or equal at posts and built up studs (HD shear transfer locations).

 11/27/2018SHEARWALL/B.W.P.-EXTWOODY TOWNSENDFAIL11/27/2018 4:44:14 PM No one on site. Owner or contractor needs to be on site because questions need to be answered to proceed with this project. Roofing installed without inspection and underfloor frame and plumbing are not approved. Lights will need to be provided to inspect under floor framing, plumbing and shear transfer. Make contact with inspector prior to re inspection.

 04/23/2019SHEARWALL/B.W.P.-INTSCOTT YOUNGPASS

 01/17/2019SHEARWALL/B.W.P.-EXTADAM KINGSLEYPASS1/17/2019 2:54:59 PM Previous exterior Shearwall corrections are completed, attached EOR letter. ok to proceed.

 08/08/2019ROUGH ELECTRICALMIKE KNIGHTPASS

 08/08/20194-WAY ROUGH FRAMEMIKE KNIGHTFAIL8/8/2019 4:38:39 PM 1. 2" x 12" rafters at lower level do not bear on top plate. Provide full bearing or letter from engineer for scab detail used. 2. Provide full bearing left side of kitchen sink for the 4=2" x 12" rafters. 3. Provide LSU''s hangers for each garage rafter at ridge beam per plan. . Missing one cripple stud at deck and need to tighten all nuts at sill plate.

 08/15/20194-WAY ROUGH FRAMEMIKE KNIGHTPASS

 11/20/2019SHOWER PAN/TUB TESTPHILLIP MYERSPASS036227-01 MSG! -Msg! Scheduled by IVR.

 01/02/2020TEMP POWERPHILLIP MYERSPASS

 03/24/2020GAS PIPINGSCOTT YOUNGPASS040288-01 - Scheduled by IVR.3/24/2020 7:22:57 AM syoung changed Inspection Date/Time from 03/24/2020 08:00 AM to 03/24/2020 10:30 AM 3/24/2020 12:16:57 PM Verified depth and pressure on U.G. propane line to house. Unable to verify gas test on house. Do not have a pressure gauge on it under test. According to the homeowner it was removed while installing water heater.

 04/02/2020**PERMIT FINALSCOTT YOUNGFAIL040487-01 - Scheduled by IVR.4/2/2020 6:37:54 AM syoung changed Inspection Date/Time from 04/02/2020 08:00 AM to 04/02/2020 12:00 PM 4/2/2020 2:47:32 PM Back porch handrail needs to be in place. No raw and exposed wood. All junction boxes to be completed and water proof cover. Anti siphon valves on all exterior hose bibs. Kitchen counter receptacles need to be GFCI. Drip leg on water heater gas line. Garage receptacles must be GFCI. Extend water heater pressure relief to min. 16" above grade. Strap water line under deck. Cover , protect and insulate water main coming into house. Hers testing still needs to be done.

 04/02/2020CAL FIRE FINAL INSPECHRIS BOYDPASS

 04/14/2020**PERMIT FINALSCOTT YOUNGPASSeTRAKiT Inspection Request4/12/2020 11:15:58 AM 4/12/2020 11:15 AM eTRAKiT User: lapottsy Contact Name: eTRAKiT User: lapottsy Site Address: 77 TIPSOO PEAK Phone: 4256813303 e-Mail: lapottsy@yahoo.com 4/14/2020 6:45:35 AM syoung changed Inspection Date/Time from 04/14/2020 08:00 AM to 04/14/2020 11:30 AM