| CAL FIRE FINAL INSPE | CHRIS BOYD | | | |
|
03/27/2025 | ENV HEALTH RELEASE | DANIEL GRATTAN | PASS | | 3/27/2025 8:19:56 AM
The existing septic system is sized for a 5-bedroom dwelling with passing disaster septic system inspection report. Setbacks met. Pass
|
|
05/09/2025 | FOUNDATION/FOOTINGS | WOODY TOWNSEND | FAIL | | 5/9/2025 3:30:44 PM
1 install all j anchor bolts.
3. Install interior form boards to height of first pour including interior footings. Cold joint per plan but footings can't be stacked.
3. Provide compaction report. Email .
|
|
05/12/2025 | PGE ELECTRIC TAG | CHRISTOPHER ROBERTS | PASS | | 5/15/2025 7:26:01 AM
PGE electric tag ADU - Approved
|
|
05/14/2025 | FOUNDATION/FOOTINGS | RANDALL SMITH | PASS | | 5/14/2025 4:21:52 PM
All previous corrections were completed collected compaction report
|
|
05/12/2025 | **PERMIT FINAL | CHRISTOPHER ROBERTS | VOID | | |
|
05/21/2025 | PRE-SLAB | WOODY TOWNSEND | PASS | | |
|
| ROOF NAIL | DSINSPECTION | | 079073-01 - Scheduled by IVR. | |
|
06/17/2025 | SHEARWALL/B.W.P.-EXT | CHRISTOPHER ROBERTS | PARTIAL | 078993-01 - Scheduled by IVR. | 6/17/2025 3:09:57 PM
1. Provide an EOR letter for the multiple Titan anchors installed throughout.
** SHEARWALL EXTERIOR - Approved
** OKAY TO WRAP
|
|