Permit No. B24-0406 Permit Type   NRES NON RESIDENTIAL Site Address   297 ROCKERFELLER RD
BERRY CREEK, CA 95916
Applied   02/27/2024 Applicant   BRANDON MCKAY
Approved   06/27/2024 Owner   COUNTY OF BUTTE
Issued   06/27/2024 Contractor   TBD
Parent Permit No.   Description   REPL FIRE STATION(1328) APPARATUS ROOM(1552)
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

FIRE MARSHAL CLEARANCHRIS BOYD

LAND DEV FINALPWLANDDEV

ENV HEALTH RELEASEKATTY HERNANDEZHOLD FOR SEPTIC FINAL6/27/2024 9:07:39 AM PENDING SEPTIC TANK REPLACEMENT PERMIT ISSUANCE AND FINAL APPROVAL. 9/20/2024 11:21:18 AM SEPTIC TANK REPLACEMENT PERMIT ISSUED. PENDING FINAL APPROVAL OF EHS24-0269.

 10/01/2024UNDERGROUND PLUMBINGRANDALL SMITHPARTIAL10/1/2024 1:42:00 PM Firewater supply line to tank. See RFI #9 10/1/2024 3:25:05 PM Firewater supply line to tank. See RFI #9

 10/01/2024UNDERGROUND PLUMBINGRANDALL SMITHPARTIAL10/1/2024 3:25:48 PM Building drain line from building to 4 ft before septic tank. Under test for 2 hours. Ok to cover

 10/01/2024UNDERGROUND GASRANDALL SMITHPASS10/1/2024 1:42:14 PM rjsmith changed Inspection Type from CONSTRUCTION POWER to UNDERGROUND GAS 10/1/2024 3:25:12 PM rjsmith changed Inspection Type from CONSTRUCTION POWER to UNDERGROUND GAS

 10/03/2024UNDERGROUND ELECTRICRANDALL SMITHFAIL074990-01 - Scheduled by IVR.10/3/2024 9:58:09 AM rjsmith changed Inspection Type from GAS TEST to UNDERGROUND ELECTRIC 10/3/2024 4:10:25 PM 1. Provide a special inspection report showing 95% compaction in the trench as per the approved set of plans.

 10/08/2024PGE ELECTRIC TAGRANDALL SMITHPASS075073-01 MSG! -Msg! Scheduled by IVR.10/8/2024 5:17:12 PM rjsmith changed Inspection Type from ROUGH ELECTRICAL to PGE ELECTRIC TAG 10/8/2024 5:20:53 PM Tagged for construction power. Temporary

 11/13/2024SEWER(PIPE/TEST/TAP)RANDALL SMITHCANCELLED075742-01 - Scheduled by IVR.11/13/2024 9:17:43 AM Date has been changed, we only do that area on Tuesdays and Thursdays. 11/14/2024 5:13:14 AM Changed to Thursday , we do not

 11/14/2024SEWER(PIPE/TEST/TAP)RANDALL SMITHPASS

 12/09/2024UFER GROUNDRANDALL SMITHCANCELLED076121-01 - Scheduled by IVR.12/9/2024 8:56:06 AM Project manager cancelled 12/9/2024 RJS

 01/02/2025UNDER SLAB PLUMBINGWOODY TOWNSENDPASS076401-01 MSG! -Msg! Scheduled by IVR.1/2/2025 4:32:21 PM No property lines located. Setbacks will be approved at foundation inspection. Proceed at own risk.

 01/24/2025SETBACKSRANDALL SMITHPASSPM REQUEST -COORDINATION

 01/24/2025FOUNDATION/FOOTINGSRANDALL SMITHFAILPM REQUEST -COORDINATION1/24/2025 2:50:11 PM 1. Anchor bolts installed are not equal to manufacturer's specification of F1554 grade 55. Provide anchor bolts as per approved set of plans. 2. Provide special inspection report for F1454 grade 55 anchor bolts.

PIER/COLUMN FOOTINGSDSINSPECTIONVOIDED (CRW 2/14/2025)

 02/20/2025LIGHT STANDARD FTGRANDALL SMITHCANCELLED077139-02 MSG! -Msg! Scheduled by IVR.

 02/25/2025UNDERFLOOR PLUMBINGRANDALL SMITHFAIL077228-01 MSG! -Msg! Scheduled by IVR.2/25/2025 5:49:34 PM 1. Provide inspection reports from the inspector of record and NV5.

 01/28/2025FOUNDATION/FOOTINGSRANDALL SMITHPARTIAL2/26/2025 8:05:03 AM Pending concrete testing report from NV5

 01/28/2025PRE-SLABRANDALL SMITHPARTIAL2/26/2025 8:05:36 AM Pending concrete testing report from NV5

 02/27/2025FOUNDATION/FOOTINGSRANDALL SMITHCANCELLED077229-01 MSG! -Msg! Scheduled by IVR.2/27/2025 3:08:23 PM Cancelled by email

 03/04/2025PIER/COLUMN FOOTINGSRANDALL SMITHPASS077291-01 MSG! -Msg! Scheduled by IVR.3/4/2025 2:12:46 PM 2 -light standards 4 - bollard holes issaelc@unitedbuildingcontractors.com

 03/04/2025PRE-SLABRANDALL SMITHFAIL3/4/2025 2:13:06 PM 1. Pump out the water from the footings on the housekeeping pad and side walk before pouring 2. Provide dobies installed on sidewalk and vehicle stalls. 3. Provide completed compaction report from NV5. 4. Provide IOR approval. 5. Provide thickened edges at the front vehicle stalls. House keeping pad Genrator pad. Fire water pump pad 2 light standards Propane pad Well housing pad 4 bollard holes Sidewalks Vehicle stalls

 04/17/2025ROUGH FRAMERANDALL SMITHCANCELLED078002-01 MSG! -Msg! Scheduled by IVR.

 04/24/2025ROUGH FRAMEWOODY TOWNSENDFAIL078139-01 - Scheduled by IVR.4/24/2025 5:55:16 PM 1. Provide all S.I. Reports to current date. High strength bolting report required prior to frame approval. 2. Provide IOR report/confirmation that all areas up to current framing inspection have no deficiencies. 3. Per S1.1 note 12 provide certificate of compliance from metal building fabricator.

 04/24/2025ROUGH MECHANICALWOODY TOWNSENDFAIL4/24/2025 5:56:16 PM Complete all mechanical and duct work and have inspected prior to insulation. Clarify if duct leakage testing will be done. Registers installed in metal framed ceiling only at this time.

 04/24/2025ROUGH PLUMBINGWOODY TOWNSENDFAIL4/24/2025 5:56:20 PM 1. Complete all water supply rough plumbing and supports in apparatus bay and test. Rough waste, vent, water supply, gas pipe and tests approved in bath,kitchen,control room, storage and ready room. Provide IOR acceptance.

 04/24/2025ROUGH ELECTRICALWOODY TOWNSENDFAIL4/25/2025 9:14:30 AM Rough electrical conduit and boxes for bath,kitchen,ready room,storage and control rooms. 1. Provide approved plan revision to mount main service mast and weather head under eves.(complete see RFI 048) 2. Provide a complete circuit connected to new service for PGE tag authorization. 3. Bond metal building structural steel. 4. Locate or install metal pipe bonds. 5. Complete all conduit and supports for circuits that will be concealed in wall framing. Wall line C and control room. 6. Install sub panel A in storage or provide revision for surface mount sub panel. 7. Provide IOR acceptance.

 04/29/2025ROUGH FRAMERANDALL SMITHFAIL078180-01 MSG! -Msg! Scheduled by IVR.4/29/2025 5:26:37 PM 1. Provide all required certifications from original framing inspection. 2. Repair stud connection on nw corner. 3. Rough electrical is completed to the top plate except conduit to elect. boxes on north wall . Do not cover. Boxes are not made up. 4. Rough mechanical is not completed. Ok to cover all framing without corrections

 05/01/2025INSULATION (WALL)RANDALL SMITHPARTIAL078259-01 MSG! -Msg! Scheduled by IVR.5/1/2025 4:39:33 PM rjsmith changed Inspection Type from 4-WAY ROUGH FRAME to INSULATION (WALL) 5/1/2025 4:41:05 PM Provide a insulation certificate