| CAL FIRE FINAL INSPE | CHRIS BOYD | | | |
|
03/28/2024 | ENV HEALTH RELEASE | DANIEL GRATTAN | PASS | | 3/22/2024 9:06:01 AM
Pending inspection report on repairs made on tank
3/28/2024 11:49:11 AM
Tanks seam was re-sealed and re-inspected indicating it's working properly
|
|
04/10/2024 | UNDER SLAB PLUMBING | RANDALL SMITH | FAIL | | 4/10/2024 2:02:46 PM
1. Sleeve all through penetrations through footings.
|
|
04/10/2024 | FOUNDATION/FOOTINGS | RANDALL SMITH | FAIL | | 4/10/2024 2:02:54 PM
Provide dobies under the foundation rebar. Rocks are not allowed to be used as dobies. Must have a positive tie to rebar.
|
|
04/10/2024 | SETBACKS | RANDALL SMITH | PASS | | |
|
04/10/2024 | UFER GROUND | RANDALL SMITH | PASS | | |
|
04/10/2024 | FOUNDATION/FOOTINGS | RANDALL SMITH | PASS | | 4/10/2024 2:13:33 PM
All corrections were completed
|
|
04/10/2024 | UNDER SLAB PLUMBING | RANDALL SMITH | PASS | | 4/10/2024 2:14:16 PM
All corrections were completed
|
|
04/15/2024 | PRE-SLAB | RICHARD PRATT | PASS | | 4/15/2024 5:48:43 AM
rpratt changed Inspection Date/Time from 04/15/2024 08:00 AM to 04/15/2024 1:30 PM
4/15/2024 4:13:11 PM
Pre-pour slab - corrections Approved
|
|
04/15/2024 | PRE-SLAB | RICHARD PRATT | FAIL | | 4/15/2024 5:48:35 AM
rpratt changed Inspection Date/Time from 04/15/2024 08:00 AM to 04/15/2024 1:30 PM
4/15/2024 4:16:04 PM
1. Please clean out pier footing to allow 3" clearance to soil. 2. tape or otherwise seal the vapor barrier to the plumbing penetrations.
3. I will re-inspect in 1 hour.
|
|
08/28/2024 | ROOF FRAME/SHEATHING | CHRISTOPHER ROBERTS | CANCELLED | | |
|
08/28/2024 | ROOF NAIL | CHRISTOPHER ROBERTS | CANCELLED | | |
|
08/29/2024 | ROOF NAIL | WOODY TOWNSEND | FAIL | | 8/29/2024 4:34:10 PM
1. Provide approved plans and ladder to access roof.
|
|
08/29/2024 | ROOF FRAME/SHEATHING | WOODY TOWNSEND | FAIL | | 8/29/2024 4:34:17 PM
1. Provide approved plans and ladder to access roof.
|
|
09/17/2024 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | FAIL | | 9/18/2024 6:51:04 AM
1. Nail shear to mud sill at left side of garage door and rear wall per shear schedule.
2. Install ltp4s 24" o.c. At rear and front gable truss to top plate.
4. Install anchor bolts within 12" of mud sill breaks. Garage.
|
|
09/17/2024 | ROOF NAIL | WOODY TOWNSEND | PASS | | |
|
10/23/2024 | SHEARWALL/B.W.P.-EXT | RICHARD PRATT | FAIL W/RE-INSP FEE | | 10/23/2024 6:19:21 AM
rpratt changed Inspection Date/Time from 10/23/2024 08:00 AM to 10/23/2024 10:30 AM
10/23/2024 11:55:50 AM
Complete the previous inspection correction items;
WET 9/18/2024 6:51:04 AM
1. Nail shear to mud sill at left side of garage door and rear wall per shear schedule.
2. Install ltp4s 24%34 o.c. At rear and front gable truss to top plate.
3. Install anchor bolts within 12%34 of mud sill breaks.
Pay re-inspection fee, the recall the inspection when completed.
|
|
| SHEAR TRANSFER | DSINSPECTION | | eTRAKiT Inspection Request | 10/25/2024 2:10:32 PM
10/25/2024 2:10 PM ELI ENGINEERING INC
Contact Name: ELI ENGINEERING INC
Site Address: 6356 ZUCKERMAN CT
Phone: 2096134201
e-Mail: EFRENSOSA@ME.COM
|
|
11/01/2024 | SHEARWALL/B.W.P.-EXT | RICHARD PRATT | CANCELLED | | 11/1/2024 5:34:33 AM
rpratt changed Inspection Date/Time from 11/01/2024 08:00 AM to 11/01/2024 11:30 AM
11/1/2024 8:29:52 PM
Contractor cancelled with the permit center at 0819 hrs.
|
|
11/07/2024 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | FAIL | | 11/7/2024 6:02:15 AM
Contractor showed up and said they were not ready for inspection.
|
|
11/13/2024 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | FAIL | | 11/13/2024 6:31:15 AM
Have an Approved stamped set of plans onsite.
|
|
12/13/2024 | ROOF FRAME/SHEATHING | RICHARD PRATT | CANCELLED | eTRAKiT Inspection Request | 12/12/2024 11:31:38 AM
12/12/2024 11:31 AM ELI ENGINEERING INC
Contact Name: ELI ENGINEERING INC
Site Address: 6356 ZUCKERMAN CT
Phone: 2096134201
e-Mail: EFRENSOSA@ME.COM
12/13/2024 5:14:34 AM
rpratt changed Inspection Date/Time from 12/13/2024 08:00 AM to 12/13/2024 1:00 PM
12/13/2024 6:53:51 AM
Cancelled due to rain and safety concerns.
|
|
12/17/2024 | SHEARWALL/B.W.P.-EXT | RANDALL SMITH | FAIL | eTRAKiT Inspection Request | 12/16/2024 10:05:16 AM
12/16/2024 10:05 AM ELI ENGINEERING INC
Contact Name: ELI ENGINEERING INC
Site Address: 6356 ZUCKERMAN CT
Phone: 2096134201
e-Mail: EFRENSOSA@ME.COM
12/17/2024 8:42:07 AM
Good morning
Your exterior shear wall inspection for today has been cancelled due to outstanding fees being owed. Please pay the outstanding fees and call to schedule an inspection.
Rand Smith
Butte County Building Inspector
|
|
12/19/2024 | SHEARWALL/B.W.P.-EXT | CHRISTOPHER ROBERTS | FAIL W/RE-INSP FEE | | 12/19/2024 3:06:16 PM
1. Nail shear to mud sill throughout building ( marked in blue keel ) remove shiners and renail to bottom plate. Remove shiners on rear gable and re-nail.
2. Install ltp4s 24%34 o.c. At rear and front gable truss to top plate.
3. Nail off seam above window in NW corner of bedroom.
4. Provide a nut for anchor or provide a Titan anchor in SE corner of garage.
Pay re-inspection fee, complete work, and recall inspection.
|
|
12/19/2024 | ROOF NAIL | CHRISTOPHER ROBERTS | FAIL | | 12/19/2024 3:06:20 PM
1. Spans for field nailing more than 12" in multiple spots throughout roof. Provide proper nailing of 12" apart in field.
2. New truss calcs are in review with plan check as of 12/19/24. Provide approved stamped truss calcs when approved by County.
Complete work and recall inspection.
|
|
01/02/2025 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | PASS | 076396-01 - Scheduled by IVR. | 1/3/2025 5:55:48 AM
1. Romex run throughout the attic space must be separated and not stacked together more than 3 .
2. All previous corrections have been completed.
Walked the roof and approved roof nail , recheck of original roof plans in review. Interior inspection for roof can be looked at next inspection. Ok to cover .
1/3/2025 5:59:41 AM
1. Romex run throughout the attic space must be separated and not stacked together more than 3 .
2. All previous corrections have been completed.
Walked the roof and approved roof nail , recheck of original roof plans in review. Interior inspection for roof can be looked at next inspection. Ok to cover .
|
|
03/19/2025 | 4-WAY ROUGH FRAME | CHRISTOPHER ROBERTS | CANCELLED | 077599-01 - Scheduled by IVR. | 3/19/2025 12:47:37 PM
Inspection canceled due to no fire sprinkler inspection called in.
|
|
03/20/2025 | 4-WAY ROUGH FRAME | CHRISTOPHER ROBERTS | PASS | 077609-01 - Scheduled by IVR. | 3/20/2025 2:03:08 PM
4-way rough frame - Approved
Sprinkler layout approved.
|
|
04/29/2025 | STUCCO (LATH) | WOODY TOWNSEND | FAIL | AM PLEASE | 4/29/2025 4:19:14 PM
1. Provide minimum 1" from bottom of weep screed to concrete at front covered patio.
2. Secure all lath at multiple areas.
3. Install Amin service panel. Lath was left loose at this location.
|
|
| STUCCO (LATH) | DSINSPECTION | | VOIDED (CRW 5/12/2025) | |
|