07/12/2024 | FOUNDATION/FOOTINGS | CHRISTOPHER ROBERTS | PASS | | 7/12/2024 12:24:41 PM
Foundation/footings - Approved
|
|
07/11/2024 | UNDER SLAB PLUMBING | SCOTT YOUNG | FAIL | | 7/12/2024 3:29:19 PM
Abs not holding under test , filled at 9:30 in the morning, at 1:30 that day it was down 8'
All pipe joints have been covered with gravel . Unable to see joints.
Clear all joints and refill for next inspection.
|
|
07/11/2024 | FOUNDATION/FOOTINGS | SCOTT YOUNG | PARTIAL | | 7/12/2024 3:29:27 PM
Footing and foundation approved but pre slab failed.
|
|
07/16/2024 | UNDER SLAB PLUMBING | SCOTT YOUNG | FAIL | | 7/16/2024 1:05:14 PM
Not ready
7/16/2024 2:46:19 PM
Not ready
|
|
07/18/2024 | UNDER SLAB PLUMBING | RICHARD PRATT | PASS | | 7/18/2024 3:25:40 AM
rpratt changed Inspection Date/Time from 07/18/2024 08:00 AM to 07/18/2024 09:30 AM
7/18/2024 10:15:12 AM
Under slab plumbing- Approved by CRoberts 7.12.24
|
|
07/18/2024 | PRE-SLAB | RICHARD PRATT | PASS | | 7/18/2024 5:50:21 PM
Pre pour slab sod and garage - Approved
7/22/2024 5:20:53 AM
Pre pour slab sod and garage - Approved
|
|
07/18/2024 | SETBACKS | RICHARD PRATT | PASS | | 7/18/2024 5:50:34 PM
Setbacks - checked and Approved
7/22/2024 5:21:06 AM
Setbacks - checked and Approved
|
|
08/22/2024 | SHEARWALL/B.W.P.-EXT | SCOTT YOUNG | PASS | | 8/22/2024 6:28:10 AM
Exterior shearwall-Approved
|
|
08/22/2024 | ROOF NAIL | SCOTT YOUNG | PASS | | 8/22/2024 6:28:20 AM
Roof nail-Approved
|
|
09/13/2024 | PROGRESS INSPECTION | SCOTT YOUNG | PASS | | 9/17/2024 8:43:59 AM
This inspection was for soffit framing, electrical placed in the soffit, prior to them closing it up to where it would not be accessible.
|
|
09/23/2024 | 4-WAY ROUGH FRAME | WOODY TOWNSEND | FAIL | 074817-01 - Scheduled by IVR. | 9/23/2024 4:51:46 PM
1. Provide County Stamped approved plans.
2. Connect all moister exhaust ducts to fans.
3. Cover all HVAC registers. Laundry and kitchen.
4. Provide mid support for pvc condensate lines.
5. Clarify kitchen counter receptacle spacing requirements at kitchen sink. Receptacles shall be within 2' of all counter top edges including sink break.
6. Support Fire place conductor.
7. Complete circuits above kitchen island. Install elec. box.
8. Bond all metal electrical outlet boxes including exterior.
9. Install feeders to sub panel.
10. Install clean out at garage sink.
11. Wire exterior receptacle within 25' of AC condenser.
12. Install doors around fire place.
13. Complete electrical circuit to attic HVAC unit.
14. Frame attic access.
15. Provide approved revised Fire sprinkler plans for additional sprinkler heads in great room and loft.
Inspection not complete without approved and revised plans.
|
|
10/04/2024 | 4-WAY ROUGH FRAME | RICHARD PRATT | FAIL | | 10/4/2024 5:37:29 AM
rpratt changed Inspection Date/Time from 10/04/2024 08:00 AM to 10/04/2024 08:30 AM
10/4/2024 1:00:18 PM
1. Provide pressure blocking between the studs backing up to the truss side pressure blocks or equal. As per details 6, 7, & 9 on S2 & S5.
2. All previous correction items have been completed.
3. Recall inspection when the above is completed.
|
|
10/08/2024 | 4-WAY ROUGH FRAME | RICHARD PRATT | PASS | | 10/8/2024 6:19:21 AM
rpratt changed Inspection Date/Time from 10/08/2024 08:00 AM to 10/08/2024 10:30 AM
10/8/2024 9:22:29 PM
4way frame and trades - Approved
|
|
11/21/2024 | ENV HEALTH RELEASE | DANIEL GRATTAN | PARTIAL | | 11/21/2024 1:12:37 PM
PENDING DISINFECTION OF WELL, TOTAL COLIFORM OVER 200
1/24/2025 3:44:42 PM
Hi Simone,
This is in response to your voicemail. If you take a look at your well results, you can see that the total coliform is over 200 mg/L which fails drinking water standards. It is rare when we see it that high. When we have a sample like this, we require the well to be disinfected and be sampled twice and have two consecutive negative tests. Let me know if you have any other questions for this process.
Thank you,
Danny Grattan
Environmental Health Specialist I
Public Health | Butte County, CA
202 Mira Loma Drive | Oroville, CA 95965
T: 530.552.4028 | F:530.538.5339
|
|
12/23/2024 | SHOWER PAN/TUB TEST | WOODY TOWNSEND | PASS | 076344-01 - Scheduled by IVR. | 12/23/2024 3:55:28 PM
2 shower pans in dwelling approved
|
|
12/23/2024 | UNDERGROUND CONDUIT | WOODY TOWNSEND | PASS | | |
|
12/23/2024 | UNDERGROUND WATER PI | WOODY TOWNSEND | PASS | | |
|
01/17/2025 | GAS TEST | CHRISTOPHER ROBERTS | PASS | | 1/17/2025 2:27:50 PM
Gas test for house line - Approved
|
|
01/17/2025 | GAS PIPING | CHRISTOPHER ROBERTS | PASS | 076673-01 - Scheduled by IVR. | 1/17/2025 2:27:29 PM
1. Poly gas line installed on 1/16/25 by propane company. Homeowner stated that gas line was filled after installation of tank. PSI gauge is currently at 0 PSI. Repair leak in poly gas line.
1/22/2025 7:18:19 AM
Gas line was repaired.
Gas piping/trench - Approved
1/22/25 CR
|
|
| SHOWER PAN/TUB TEST | DSINSPECTION | | VOIDED (CRW 1/22/2025) | |
|
01/22/2025 | GAS TEST | CHRISTOPHER ROBERTS | CANCELLED | | 1/22/2025 11:19:09 AM
Gas test inspection conducted on 1/17/25
|
|
01/23/2025 | SHOWER PAN/TUB TEST | WOODY TOWNSEND | PASS | 076749-02 - Scheduled by IVR. | 1/23/2025 5:06:27 PM
Garage shower pan approved
|
|
01/24/2025 | CAL FIRE FINAL INSPE | CHRIS BOYD | PARTIAL | | 1/24/2025 12:58:46 PM
Post address on structure per our requirements. Left a VM with Simone as well as a business card onsite to notify her.
|
|