06/29/2023 | FOUNDATION/FOOTINGS | RANDALL SMITH | PARTIAL | REQ AM | 6/29/2023 4:52:44 PM
Spread footings. Foundation existing. Will need special inspection for Simpson titen used as a hold down as per plans.
Ok to pour
|
|
06/29/2023 | PRE-SLAB | RANDALL SMITH | PASS | | 6/29/2023 4:53:04 PM
Ok to pour
|
|
07/18/2023 | ROOF NAIL | CHRISTOPHER ROBERTS | PASS | | 7/18/2023 2:47:43 PM
1. Install H1 or equal on bottom of all trusses.
** inspect at 4-way
** roof nail APPROVED, okay to cover.
|
|
07/18/2023 | SHEARWALL/B.W.P.-EXT | CHRISTOPHER ROBERTS | FAIL | | 7/18/2023 2:47:51 PM
1. Provide special inspection report for Titan HD bolts through foundation.
** okay to wrap.
** Shearwall ext. inspected and APPROVED
|
|
09/27/2023 | ROUGH FRAME | RANDALL SMITH | PASS | | 9/27/2023 3:21:44 PM
Received special inspection report for Titens used on east side of big garage door.
|
|
09/27/2023 | ROUGH ELECTRICAL | RANDALL SMITH | PASS | | 9/27/2023 3:21:48 PM
Received special inspection report for Titens used on east side of big garage door.
|
|
12/12/2023 | **PERMIT FINAL | RICHARD PRATT | PASS | | 12/12/2023 5:49:47 AM
rpratt changed Inspection Date/Time from 12/12/2023 08:00 AM to 12/12/2023 10:00 AM
12/12/2023 2:45:40 PM
Snow damage repair Final - Approved
|
|