| CAL FIRE FINAL INSPE | CHRIS BOYD | | | |
|
08/24/2023 | FOUNDATION/FOOTINGS | LARRY AKERS | CANCELLED | | |
|
08/25/2023 | FOUNDATION/FOOTINGS | RAYMOND SANDOVAL | PASS | 068506-01 - Scheduled by IVR. | |
|
09/21/2023 | PRE-SLAB | RAYMOND SANDOVAL | PASS | 068988-01 - Scheduled by IVR. | |
|
09/25/2023 | UNDER SLAB PLUMBING | CHRISTOPHER ROBERTS | PASS | 069045-01 - Scheduled by IVR. | 9/25/2023 12:11:48 PM
Under slab plumbing - Approved
|
|
02/13/2024 | ROOF NAIL | SCOTT YOUNG | FAIL | 071243-01 - Scheduled by IVR. | 2/14/2024 6:22:35 AM
Not ready for inspection.
See attachments for pictures
|
|
02/15/2024 | ROUGH ELECTRICAL | SCOTT YOUNG | CANCELLED | 071243-02 - Scheduled by IVR. | 2/15/2024 6:11:12 AM
Cancelled by contractor.
|
|
02/23/2024 | ROOF NAIL | CHRISTOPHER ROBERTS | PARTIAL | 071388-01 - Scheduled by IVR. | 2/23/2024 2:21:38 PM
1. Missing H1's or equal on interior trusses in main room.
2. Gable end bracing on front of home required.
3. Web bracing from gable ends all the way through in truss webbing required per plans.
Roof Nail - Approved
OKAY TO COVER ROOF
|
|
03/05/2024 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | FAIL | 071541-01 - Scheduled by IVR. | 3/5/2024 4:29:38 PM
1. Install 4x studs at abutting panel edges for #4 shear walls.
2. Provide approved plan revisions including energy calcs for new windows west wall.
All exterior nailing per plan except new window locations.
Cover at own risk.
|
|
03/27/2024 | PGE ELECTRIC TAG | RANDALL SMITH | PASS | | 3/27/2024 2:47:47 PM
Tagged 400a MPU. Will need second ground rod before final
|
|
06/06/2024 | ROUGH FRAME | SCOTT YOUNG | FAIL | 073024-03 - Scheduled by IVR. | 6/6/2024 6:12:04 AM
Not ready for 4-way rough frame .
Fire sprinklers not done
Plumbing not done.
Complete and call for reinspection when ready.
|
|
06/06/2024 | GAS PIPING | SCOTT YOUNG | CANCELLED | 073024-02 MSG! -Msg! Scheduled by IVR. | |
|
06/06/2024 | ROUGH ELECTRICAL | SCOTT YOUNG | CANCELLED | 073024-01 - Scheduled by IVR. | |
|
07/11/2024 | 4-WAY ROUGH FRAME | RICHARD PRATT | CANCELLED | No Fire Sprinkler permit. | 7/11/2024 5:52:41 PM
Fire Sprinkler permit has not made it through plan review.
|
|
07/24/2024 | 4-WAY ROUGH FRAME | CHRISTOPHER ROBERTS | FAIL | 073796-01 - Scheduled by IVR. | 7/24/2024 3:24:44 PM
1. Cover all HVAC registers throughout.
2. Insulate behind bathtub and cover or fill in gap for tub plumbing.
3. Add strap to break in bottom plate behind tub.
4. Insulate all hot water lines throughout.
5. Provide plumbing under test at time of inspection.
6. Seal off all holes leading to outside.
7. Cut in attic hatch.
Complete work and call for re-inspection.
|
|
07/31/2024 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PASS | | 7/31/2024 7:18:27 AM
Received, reviewed and approved revised plans and energy calcs for new window.
|
|
08/15/2024 | 4-WAY ROUGH FRAME | RANDALL SMITH | FAIL | PM REQUEST | 8/15/2024 4:01:33 PM
1. Provide a 22 by 30 inch attic access with a walkway and working platform to service the air handler unit. Will be checked at final.
All other corrections from the 4 way inspection were completed.
Ok to insulate.
|
|
07/10/2025 | **PERMIT FINAL | CHRISTOPHER ROBERTS | CANCELLED | AM | |
|
07/24/2025 | ENV HEALTH RELEASE | KATTY HERNANDEZ | PASS | SEE NOTES | 8/2/2023 1:29:43 PM
PENDING VERIFICATION OF POTABLE WATER.
7/24/2025 2:31:10 PM
RECEIVED COLIFORM BACTERIA REPORT AND NITRATE REPORT.
|
|