| ENV HEALTH RELEASE | ALANA KONG | PASS | | |
|
06/28/2023 | ROUGH PLUMBING | CHRISTOPHER ROBERTS | PASS | 067509-01 - Scheduled by IVR. | 6/28/2023 2:52:01 PM
Rough plumbing - Approved
|
|
06/28/2023 | ROUGH PLUMBING | WOODY TOWNSEND | CANCELLED | 067520-01 - Scheduled by IVR. | |
|
07/05/2023 | PIER/COLUMN FOOTINGS | WOODY TOWNSEND | FAIL | 067521-01 - Scheduled by IVR. | 7/5/2023 5:32:39 PM
Install rebar in pier footings.
|
|
07/05/2023 | FOUNDATION/FOOTINGS | WOODY TOWNSEND | PASS | 067520-02 - Scheduled by IVR. | 7/5/2023 3:21:36 PM
Provide letter from engineer for sand over vapor barrier or remove.
7/5/2023 5:06:08 PM
R506.2.3 Vapor Retarder
A minimum 10-mil (0.010 inch; 0.254 mm) vapor retarder conforming to ASTM E1745 Class A requirements with joints lapped not less than 6 inches (152 mm) shall be placed between the concrete floor slab and the base course or the prepared subgrade where a base course does not exist.
4.505.2.1 Capillary Break
A capillary break shall be installed in compliance with at least one of the following:
A 4-inch-thick (101.6 mm) base of 1/2 inch (12.7 mm) or larger clean aggregate shall be provided with a vapor retarder in direct contact with concrete and a concrete mix design, which will address bleeding, shrinkage and curling, shall be used. For additional information, see American Concrete Institute, ACI 302.2R-06.
Other equivalent methods approved by the enforcing agency.
A slab design specified by a licensed design professional.
7/5/2023 5:25:16 PM
Received letter from engineer and attached. Foundation approved.
|
|
07/06/2023 | PIER/COLUMN FOOTINGS | RAYMOND SANDOVAL | PASS | 067522-01 - Scheduled by IVR. | 7/6/2023 10:17:04 AM
Previous corrections completed
|
|
07/06/2023 | PRE-SLAB | RAYMOND SANDOVAL | PASS | | |
|
07/10/2023 | GAS PIPING | WOODY TOWNSEND | FAIL | 067630-01 - Scheduled by IVR. | 7/10/2023 3:45:27 PM
No piping to inspect at this time.
|
|
07/20/2023 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PARTIAL | 067820-01 - Scheduled by IVR. | 7/20/2023 3:44:43 PM
Inspection request for 4 west side shear walls on addition only. No roof installed, trusses on back order and would like to proceed.
4 shear walls approved, see job plans for location. Shear transfer to roof will be at next inspection as no trusses yet.
|
|
07/31/2023 | ROOF NAIL | WOODY TOWNSEND | FAIL | 068032-01 - Scheduled by IVR. | 7/31/2023 4:12:22 PM
wtownsend changed Inspection Type from SHEAR TRANSFER to ROOF NAIL
7/31/2023 4:19:30 PM
Inspection requested for west side addition only.
Okay to cover roof nail in this area after engineers revision to use timber lock screws at patio rafter connection.
Will also need engineers revision for missing drag truss at interior shear wall and any shear transfer changes at this location. HDs are installed at this location. Epoxy letter attached.
|
|
08/01/2023 | ROOF NAIL | RANDALL SMITH | FAIL | 068034-01 MSG! -Msg! Scheduled by IVR. | 8/1/2023 5:06:55 PM
Contractor requested to put second layer of roof sheathing on south facing roof of west addition. 7/31/23 corrections not completed. Approved second layer of sheathing to be placed only. Can check drag truss nailing once all corrections have been completed.
7/31/2023 WET roof nail inspection
Inspection requested for west side addition only.
Okay to cover roof nail in this area after engineers revision to use timber lock screws at patio rafter connection.
Will also need engineers revision for missing drag truss at interior shear wall and any shear transfer changes at this location. HDs are installed at this location. Epoxy letter attached.
|
|
08/08/2023 | SHEARWALL/B.W.P.-EXT | RICHARD PRATT | PASS | 068190-01 - Scheduled by IVR. | 8/8/2023 2:54:41 PM
Exterior Shearwall installation - Approved
|
|
08/08/2023 | ROOF NAIL | RICHARD PRATT | PASS | | 8/8/2023 2:54:45 PM
Roof nail - Approved
|
|
08/09/2023 | ROOF NAIL | WOODY TOWNSEND | PASS | 068191-01 - Scheduled by IVR. | 8/9/2023 4:30:22 PM
All roof nail complete
|
|
08/28/2023 | 4-WAY ROUGH FRAME | WOODY TOWNSEND | PARTIAL | 068496-01 - Scheduled by IVR. | 8/28/2023 3:10:15 PM
1. Provide copy of engineers letter for interior shear connection at garage and approval and installation of Titan anchors replacing all j bolts.
2. Bond gas pipe.
Call for interior shear nail at garage after installation.
|
|
08/29/2023 | GAS TEST | CHRISTOPHER ROBERTS | PASS | 068497-01 - Scheduled by IVR. | 8/29/2023 1:27:05 PM
Gas test - APPROVED
|
|
09/07/2023 | SHEARWALL/B.W.P.-INT | LARRY AKERS | PASS | 068727-01 MSG! -Msg! Scheduled by IVR. | 9/7/2023 3:27:19 PM
Last interior shear wall approved
|
|
09/13/2023 | GAS PIPING | RAYMOND SANDOVAL | PASS | 068798-01 - Scheduled by IVR. | |
|
11/14/2023 | GAS TEST | CHRISTOPHER ROBERTS | PASS | 069941-01 MSG! -Msg! Scheduled by IVR. | 11/14/2023 10:08:38 AM
Gas test house - Approved
|
|
02/13/2025 | SHOWER PAN/TUB TEST | WOODY TOWNSEND | PASS | 077088-01 - Scheduled by IVR. | |
|
05/01/2025 | **PERMIT FINAL | WOODY TOWNSEND | FAIL | 078261-01 - Scheduled by IVR. | 5/1/2025 4:03:02 PM
1. Install landing at west exterior door.
2. Install smoke alarms in existing bedrooms.
3. Provide access to gas bond.
4. Connect house gas to underground for future LPG tank location. LPG tank will not be set at this time. Location of tank will meet setbacks when installed.
HERs approved.
.
|
|