09/14/2023 | SETBACKS | RICHARD PRATT | PASS | | 9/14/2023 1:59:23 PM
Setbacks checked and Approved
|
|
09/14/2023 | FOUNDATION/FOOTINGS | RICHARD PRATT | PASS | 068833-01 - Scheduled by IVR. | 9/14/2023 5:41:24 AM
rpratt changed Inspection Date/Time from 09/14/2023 08:00 AM to 09/14/2023 11:00 AM
9/14/2023 1:59:28 PM
Forms and footings - Approved
|
|
09/14/2023 | FORMS/STEEL/HOLDOWNS | RICHARD PRATT | PARTIAL | 068833-02 - Scheduled by IVR. | 9/14/2023 5:41:21 AM
rpratt changed Inspection Date/Time from 09/14/2023 08:00 AM to 09/14/2023 11:00 AM
9/18/2023 6:38:28 AM
Provide an Engineered Solution to the lack of a spread footing for the load above from the 2nd floor to the Building Dept. Engineer.
Project Engineer suggested a 40"x40"x12" footing with (4) #5's e.w. Contractor went with 42"x42x13" and (4) #5's e.w. See photo.
Pour at own risk.rpratt changed Inspection Date/Time from 09/14/2023 11:00 AM to 09/14/2023 2:30 PM
|
|
09/22/2023 | UNDERFLOOR FRAMING | RICHARD PRATT | PASS | 069023-01 - Scheduled by IVR. | 9/22/2023 7:03:07 AM
rpratt changed Inspection Date/Time from 09/22/2023 08:00 AM to 09/22/2023 09:30 AM
9/22/2023 11:42:46 AM
Underfloor framing at new office and new wing. - Approved
|
|
09/22/2023 | UNDERFLOOR PLUMBING | RICHARD PRATT | PASS | | 9/22/2023 11:42:49 AM
Underfloor plumbing in the new wing - Approved
|
|
09/22/2023 | UNDERGROUND PLUMBING | RICHARD PRATT | PASS | | 9/22/2023 11:42:53 AM
Underground plumbing in new break room - Approved
|
|
09/26/2023 | FLOOR NAIL | RICHARD PRATT | PASS | 069065-01 - Scheduled by IVR. | 9/26/2023 12:53:51 PM
Floor diaphragm installation and nailing - Approved
|
|
10/05/2023 | ROOF NAIL | WOODY TOWNSEND | PARTIAL | 069233-02 - Scheduled by IVR. | 10/5/2023 1:15:11 PM
Provide engineers approval to omit details s3/9 2x6 bracing when using I joist and adding full depth blocking clarifying all connections.
Okay to cover roof nail excluding west addition.
|
|
10/05/2023 | SHEARWALL/B.W.P.-EXT | WOODY TOWNSEND | PARTIAL | 069233-01 - Scheduled by IVR. | 10/5/2023 1:15:17 PM
wtownsend changed Inspection Type from SHEARWALL/B.W.P.-INT to SHEARWALL/B.W.P.-EXT
10/5/2023 3:27:30 PM
Shear approved excluding west side addition.
10/5/2023 3:27:48 PM
Shear approved excluding west side addition.
|
|
10/26/2023 | ROUGH FRAME | LARRY AKERS | PARTIAL | 069647-01 - Scheduled by IVR. | 10/26/2023 10:04:15 AM
Under floor frame at west rear approved.
|
|
11/14/2023 | ROOF NAIL | CHRISTOPHER ROBERTS | PASS | 069935-02 - Scheduled by IVR. | 11/14/2023 7:52:29 AM
croberts changed Inspection Date/Time from 11/14/2023 12:30 PM to 11/14/2023 12:00 PM
11/14/2023 11:51:28 AM
Roof nail west addition - Approved
|
|
11/14/2023 | SHEARWALL/B.W.P.-EXT | CHRISTOPHER ROBERTS | PASS | 069935-01 - Scheduled by IVR. | 11/14/2023 7:52:36 AM
croberts changed Inspection Date/Time from 11/14/2023 12:30 PM to 11/14/2023 12:00 PM
11/14/2023 11:51:35 AM
Shearwall ext. west side - Approved
|
|
12/04/2023 | 4-WAY ROUGH FRAME | RICHARD PRATT | CANCELLED | Cancelled on 12/4/2023 at 12:47 PM | |
|
12/06/2023 | 4-WAY ROUGH FRAME | LARRY AKERS | FAIL | 070208-02 - Scheduled by IVR. | 12/6/2023 10:31:21 AM
1) draft stop wall to cealing
|
|
12/06/2023 | STUCCO (LATH) | LARRY AKERS | PASS | 070196-01 - Scheduled by IVR. | |
|
12/07/2023 | 4-WAY ROUGH FRAME | LARRY AKERS | PASS | 070247-01 - Scheduled by IVR. | |
|
10/07/2024 | TAG ELECTRIC | RICHARD PRATT | FAIL | 075049-02 - Scheduled by IVR. | 10/7/2024 6:42:17 AM
rpratt changed Inspection Date/Time from 10/07/2024 08:00 AM to 10/07/2024 3:30 PM
10/8/2024 8:23:54 PM
Provide a 2nd ground rod a minimum of 6' away from the 1st or equal.
Provide someone on-site to perform the torque test.
Inspection stopped at that point.
|
|
10/07/2024 | SERVICE PANEL | RICHARD PRATT | CANCELLED | 075049-01 - Scheduled by IVR. | 10/7/2024 6:42:24 AM
rpratt changed Inspection Date/Time from 10/07/2024 08:00 AM to 10/07/2024 3:30 PM
|
|
10/09/2024 | PGE ELECTRIC TAG | WOODY TOWNSEND | PASS | 075118-01 - Scheduled by IVR. | 10/9/2024 4:42:11 PM
wtownsend changed Inspection Type from SERVICE PANEL to PGE ELECTRIC TAG
10/9/2024 4:59:43 PM
1000 amp main service connection authorized.
2nd ground rod to be disconnected from existing service and connected to new service prior to utility connection.
Complete all circuits, label and bond gas and water pipes to new service.
|
|
02/11/2025 | **PERMIT FINAL | WOODY TOWNSEND | FAIL | 077038-01 - Scheduled by IVR. | 2/11/2025 4:48:26 PM
1. Obtain department final approvals for NPDES, Land Development, Health And Fire Marshall.
2. Submit revisions for mechanical and electrical changes for approval. Mechanical units are all mini splits with no ducted unit and sub panel identifications and locations have changed. Reinspect mechanical and electrical panels after plan revisions are approved. Wiring in panels have been inspected.
3. Obtain permit for ev charging stations.
4. Post AIC rating from PGE on ARC Flash Warning at main service.
5. Bond metal gas and water pipes.
6. Provide ladder for roof inspection.
7. Provide accessible route to safe dispersal area from all exits.
8. Clear and level safe dispersal area.
9. Stripe exterior stair treads install hand rails and guide curb per AO.4/2&3.
10. Install all illuminated and tactile exit signs per plan.
11. Provide all electrical and mechanical final energy compliance installation and acceptance forms per revised mechanical plan.
|
|
| NPDES | PWLANDDEV | | VOIDED (KH1 2/12/2025) | 2/12/2025 11:06:47 AM
Inspection voided by KH1. Most recent remarks follow: During Construction
|
|
02/13/2025 | NPDES | PWLANDDEV | PASS | Final Inpsection | |
|
02/13/2025 | LAND DEV FINAL | PWLANDDEV | PASS | | |
|
02/25/2025 | ENV HEALTH RELEASE | PAUL THAO | PARTIAL | Pending septic final for release | 8/11/2022 7:46:16 PM
Reassigned P Thao 8/11/22
2/25/2025 8:33:26 AM
Proposed designer septic system was not installed. A second septic system was connected for use. Pending a certified designer's assessment of the septic system location and sizing for approval.
|
|
04/01/2025 | FIRE MARSHAL CLEARAN | CHRIS BOYD | PASS | | 4/1/2025 1:18:20 PM
Ok to final, address is posted.
|
|
| **PERMIT FINAL | DSINSPECTION | | VOIDED (CRW 7/8/2025) | |
|
07/10/2025 | **PERMIT FINAL | RANDALL SMITH | FAIL | 079353-02 - Scheduled by IVR. | 7/10/2025 5:23:52 PM
1. Provide final approval from Butte County Environmental Health.
2. Provide a maximum 15 amp breaker or equal for mini split unit d.
3. Provide a maximum 15 amp breaker for unit c.
4. Secure all mini split units in 2 locations.
5.Label 20 amp breaker in sub panel 3 row 26.
6. Provide maximum 15 amp breakers in mini split units A&B.
7. Hand rail at the exterior of the staff lounge is loose. Repair, replace or equal.
8. Provide all electrical, indoor lighting and mechanical final energy compliance installation and acceptance forms.
9. Provide listing data showing installed 60 amp breakers are required for the ev chargers or provide 40 amp breakers for the ev chargers as per revised set of plans or equal.
10. Call for reinspection when corrections are completed.
Bkennedy@gpdevelopmentcorp.com
|
|
07/15/2025 | **PERMIT FINAL | SCOTT YOUNG | PARTIAL | 079433-01 - Scheduled by IVR. | 7/14/2025 10:09:33 AM
ENERGY COMPLIANCE ATTACHED TO PERMIT
7/16/2025 7:46:23 AM
All previous corrections have been completed.
Final pending Environmental health sign off.
7/16/2025 7:47:27 AM
All previous corrections have been completed.
Final pending Environmental health sign off.
7/16/2025 7:48:19 AM
All previous corrections have been completed.
Final pending Environmental health sign off.
7/16/2025 7:49:36 AM
All previous corrections have been completed.
Final pending Environmental health sign off.
7/16/2025 7:50:34 AM
All previous corrections have been completed.
Final pending Environmental health sign off.
|
|